An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ANU Shutdown StatusAEM meeting Cons Gattuso 7 May 2012

  2. Accelerator and NuMI Upgrades • Recycler Ring, RR • New injection line into RR • New extraction line from RR • New 53 MHz RF system • Instrumentation Upgrades • New abort kickers • Decommissioning of pbar components • Main Injector • Two 53 MHz cavities • Quad Power Supply Upgrade -Done • Low Level RF System • NuMI • Change to medium energy n beam configuration (new target, horn, configuration) • Cooling & power supply upgrades Cons Gattuso, AEM

  3. Big Picture Cons Gattuso

  4. NuMI Work Status • Monday April 30th • Horn and power supply test • Ran System at the NoVA era 1.333 sec rep rate successfully • Tuesday May 1st • Target Hall was repaired for Supervised Access…. • Rad surveys done • Crane electronics were installed • Shielding wall removed • WednesdayMay 2nd • RAW water system • System drained • Filter changed out • DI Bottles removed Cons Gattuso

  5. NuMI Work Status • Thursday May 3nd • Drained glycol from TP chiller (900 Gallons) • Dehumidifier upgrade • Disconnect cooling lines to dehumidifier coil box • Started initial electrical work • Electrical work • Install supplemental lighting and electrical services were added to add in the shutdown work. • Horn 2 work • Started disconnecting Horn 2 RAW piping in Target Hall • Removed strip line cage Cons Gattuso

  6. NuMI Plans For The Week • Dehumidifier upgrade • Re-pipe system • Munters Coil & housing upgrades • NOvA Cooling Coil Installation • Work runs from 5/7 through 5/18 • Provides additional cooling for TP and Chase air handling system • Install new lighting & electrical service on top of and behind work cell • Install Target Hall rail system • Installation of the 3Q120 Quads at the Q113, Q114, & Q120 • Transport and installation of Quads to retarget enclosure Cons Gattuso

  7. Main Injector Tunnel Work status • Monday April 30th • MI power supply tests • Tuesday May 1st • MI rad survey complete • Doors re-cored • Thursday May 3rd • A short tunnel access was complete to closes all RR and MI beam Valves • Friday May 4th - Monday May 7th • Tunnel relamping Cons Gattuso

  8. This weeks plans Next week: Task specific accesses only Special approval will be needed for any tunnel before May 9th Monday, May 7th Water Group accessing to layout MI-14 water work Wednesday, May 9th Fire testing fire protection systems in MI/RR – NO ACCESS until completed (09:00 to 12:00) Accessing to clear MI-60 MVA Thursday, May 10th Accessing to clear MI-60 MVA As Founds for 614 and injection region Power Supply isolation for MI-8 work Friday, May 11th Staging equipment for following week General access begins Monday, May 14th