1 / 8

LINAC HINS/Proton Driver Civil Design Synergies

LINAC HINS/Proton Driver Civil Design Synergies. Dixon Bogert Fermilab Accelerator Advisory Committee May 10 th – 12 th , 2006. Reporting Work by FESS – Elaine McCluskey And Chuck Federowicz Tom Lackowski Paul Lahn Rod Walton Gary Van Zandbergen. Outline. Siting – Inside Main Ring

etta
Download Presentation

LINAC HINS/Proton Driver Civil Design Synergies

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LINAC HINS/Proton DriverCivil Design Synergies Dixon Bogert Fermilab Accelerator Advisory Committee May 10th – 12th , 2006 Reporting Work by FESS – Elaine McCluskey And Chuck Federowicz Tom Lackowski Paul Lahn Rod Walton Gary Van Zandbergen HINS/PD Civil – AAC Review May 10-12, 2006 Dixon Bogert

  2. Outline • Siting – Inside Main Ring • Major Elements of Construction for HINS & ILC • Overview on Site Plan • Cross-sections of tunnels/service building • HINS • ILC • Plans of HINS Klystron Gallery & ILC Service Tunnel • ILC TF Deficiencies with respect to HINS facility • HINS Consultant Engineering Work in FY06 HINS/PD Civil – AAC Review May 10-12, 2006 Dixon Bogert

  3. Linac Proton Driver Site Plan 5 GeV ILC TF LINAC 0 - 8 GeV HINS LINAC HINS/PD Civil – AAC Review May 10-12, 2006 Dixon Bogert

  4. HINS Linac Enclosure/Klystron Gallery HINS/PD Civil – AAC Review May 10-12, 2006 Dixon Bogert

  5. ILC Twin Tunnels HINS/PD Civil – AAC Review May 10-12, 2006 Dixon Bogert

  6. Klystron Gallery (HINS)/Tunnel (ILC) 120 ft HINS GALLERY 118 ft ILC SERVICE TUNNEL HINS/PD Civil – AAC Review May 10-12, 2006 Dixon Bogert

  7. ILC TF Deficiencies w.r.t. HINS Facility • Below grade service gallery presents operational difficulties for HINS • In ILC service tunnel, equipment arrangement &tunnel connections to beam tunnel would make HINS upgrade to 2 MW beam difficult. HINS planned for this upgrade. • Round ILC beam tunnel section is markedly smaller than HINS tunnel • Future uses such as recirculating muon acceleration not accounted for. HINS/PD Civil – AAC Review May 10-12, 2006 Dixon Bogert

  8. HINS Consultant Work FY06 • Life Safety study completed that established code-related occupancy, exiting, and fire protection requirements for the proposed facility • Hydrogeologic borings to determine horizontal and vertical groundwater transport in vicinity of proposed linac absorber • Wetland delineation for south half of Tevatron Ring to scope what wetland mitigation would be required for installation of new facility in this region HINS/PD Civil – AAC Review May 10-12, 2006 Dixon Bogert