An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2013 Business Plan Capital Plan

  2. Transportation Infrastructure Estimated Replacement Value of $65.8 - $72.3 million • 2013 Capital Project Budget of $1,875,000 • Key Projects: • Traffic/pedestrian safety improvements • Blakely Road repave • Harris Road repave (Cranberry Slough to Old Dewdney) • Old Dewdney Trunk Road (Sharpe to Harris Road) • Neaves Road (S. Alouette River to N. Alouette River) • Replacement of Thompson Road Bridge 2013 Budgeted Provision - $1,330,000 (plus interest)

  3. Waterworks Infrastructure Estimated Replacement Value of $51.5 - $59.5 million • 2013 Capital Project Budget of $1,005,000 • Key Projects: • Baynes Road AC main replacement • 194B Street & Davison Road main replacement • Final phase of water meter replacements 2013 Budgeted Provision - $754,016 (plus interest)

  4. Sanitary Sewer Infrastructure Estimated Replacement Value of $23.5 - $25.3 million • 2013 Capital Project Budget of $540,000 • Key Projects: • Refurbishment of sewer mains • Video of sewer main condition • Installation of fall protection davits at all lift stations 2013 Budgeted Provision - $356,633 (plus interest)

  5. Drainage Infrastructure • 2013 Capital Project Budget of $5,890,000 • Key Projects: • Replacement of Pump Station No. 4 • Replacement of pumps in Baynes Road pump station • Automated trash racks at McKechnie Pump Station Estimated Replacement Value of $49.5 - $52.4 million 2013 Budgeted Provision - $406,128 (plus interest)

  6. Dyke Infrastructure • 2013 Capital Project Budget of $40,000 • Miscellaneous repairs and topping only Estimated Replacement Value of $43.4 - $54.0 million 2013 Budgeted Provision - $35,000 (plus interest)

  7. Equipment Replacement Fleet, Fire Apparatus, IT, Recreation Equipment • 2013 Capital Project Budgets: • Fleet - $237,500 • IT - $389,500 • Recreation Equipment - $41,000 • Key Projects: • Replacement of Rollpac roller • Replacement of Backhoe • Council Chambers Audio/ Video distribution system • Network Switching Hardware • Geographic Information System Upgrade • Vadim and Financial Software Upgrade • New Network Monitoring Dashboard • EOC Call Center Estimated Replacement Value $10.3 – 11.3 million 2013 Budgeted Provision - $510,000 (plus interest)

  8. Facilities Municipal Buildings, Recreation Facilities, Parks • 2013 Capital Project Budgets: • Parks - $325,000 • Recreation Facilities - $1,405,000 • Municipal Buildings- $261,000 • Key Projects: • PMFRC Renovation • Expand CPO Space (Decision Package) • Works yard Wash Rack Estimated Replacement Value $48.2 – $53.1 million 2013 Budgeted Provision - $631,000 (plus interest)

  9. Proposed Capital Plan Summary

  10. Capital Plan Questions?