90 likes | 219 Views
Project Update Goat Island Park Ph. 2 Town of Cramerton. December 19 th , 2013. Overall Master Plan – Phase 2. Master Plan – Phase 2. Phase 2-Amenities Pedestrian Bridge (3) Cornhole Boards (2) Table Tennis Dog Park Playground Observation Platform. Bridge Design. Bridge Approach
E N D
Project Update Goat Island Park Ph. 2 Town of Cramerton December 19th, 2013
Master Plan – Phase 2 Phase 2-Amenities Pedestrian Bridge (3) Cornhole Boards (2) Table Tennis Dog Park Playground Observation Platform
Bridge Design Bridge Approach 120’ span Prefabricated Bridge 165’ span Bridge Approach 80’ span Capstone Style Prefabricated Bridge 165’ Center Span, Painted Black with Decorative Lighting
SCHEDULE Project Team Meeting January 9, 2014 Complete Design January 31, 2014 Advertise for Construction Bids February 5, 2014 Open Construction Bids February 28, 2014 Award Construction Contract March 20, 2014 Begin Construction April 5, 2014 Complete Construction December 15, 2014
Goat Island Project Questions or Comments?