1 / 14

Thinking Twice About Transmission (and its alternatives)

Thinking Twice About Transmission (and its alternatives). NEDRI Participants meeting June 4, 2002 Richard Cowart. Wholesale barriers to load management and efficiency. Supply-only bidding Load profiling by pools and RTOs Reliability rules and practices excluding demand-side resources

gaenor
Download Presentation

Thinking Twice About Transmission (and its alternatives)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Thinking Twice About Transmission(and its alternatives) NEDRI Participants meeting June 4, 2002 Richard Cowart

  2. Wholesale barriers toload managementandefficiency • Supply-only bidding • Load profiling by pools and RTOs • Reliability rules and practices excluding demand-side resources • Subsidies for wires and turbines • Transmission pricing and expansion policies can undercut low-cost demand-side resources

  3. Starting points: How much transmission do we need? • Compared to what? • Consumers don’t purchase transmission • Transmission is a service with substitutes • Load center resources of all kinds: G,DG,DR,EE • Transmission bottlenecks: reduced options, thinner markets (market breadth as an issue) • Demand-side bottlenecks: reduced options, thinner markets (depth as an option) • Challenge: how much geographic breadth is needed, and how much market depth?

  4. Load Densities - Southern New England

  5. Congestion and Reliability • Congestion statistics: • increase in TLRs • higher costs for load pocket power • how much is real? • Is congestion a reliability problem, or an economic signal? • A signal of what? Too little transmission, or too little load management? Surplus power for export? Too much remote generation, not enough in the load center? • What is the efficient level of congestion?

  6. Pricing and Socializing - No Big Deal? • “It’s Only 10%” • “Tasty Treats for Transmission” • The Transmission Policy Barbell: • Competitive effects on different generators • Effects on the market value of load-side resources • Remote generation and “coal by wire” • Dynamic effects - signals to investors • Dynamic effects - logrolling on the wires

  7. Balanced Grid Management Five options to consider • 1. First, fix the underlying power markets • 2. Cost-based transmission rates • 3. Broad-based transmission planning process really examines alternatives • 4. Efficient Reliability Standard for costs proposed to be rolled-in or socialized • 5. “Open Season” to test planning outcomes in the market

  8. My screensaver Year 2000

  9. (1) Improving power markets • Locational pricing, demand response, and time-based wholesale costing are foundation stones for transmission needs analysis • Market abuses and sham transactions are no basis for need determinations

  10. (2) Transmission Rates • Market lesson: The cost of electricity varies by time and location. • Why (a) deaverage powerprices by time and location, while (b) moving to postage-stamp transmission rates across times and locations? • Should expensive new facilities be averaged in with low-cost facilities and recovered on a rolled-in basis? • Does this affect the viability of non-transmission alternatives? • Highway metaphors for disk drives

  11. (3)The Challenge of Transmission Planning • FERC:RTO has Transmission planning responsibility • NTGS: “Regional planning processes must consider transmission and non-transmission alternatives when trying to eliminate bottlenecks.” • Challenges: (a) integrated analysis in a de-integrated industry (b) transmission system is regional, but siting decisions and transmission alternatives are local • How can the ISOs weigh alternatives?

  12. (4) Efficient Reliability Decision Rule • Before “socializing” the costs of a proposed reliability-enhancing investment through uplift or tariff, ISO-NE (and PUCs and FERC) should require a showing: • that the relevant market is fully open to demand-side as well as supply resources; • that the proposed investment is the lowest cost, reasonably-available measure to correct a remaining market failure; and • that benefits will be widespread, and thus appropriate for broad-based funding.

  13. (5) Open Season for Transmission and Alternatives • NTGS: “...opportunities for customers to reduce their electricity demands voluntarily, and targeted energy-efficiency and distributed generation, should be coordinated within regional markets.” • How to test the preferred alternative in transmission planning? • One answer: Put it out to bid • Essential component: Winning bid has the same security of payment as the transmission proposal would have.

  14. Questions for discussion • Should New England’s transmission tariffs be reviewed for effects on competitiveness of load-center supply and demand resources? • How can the region create a balanced transmission planning process? • Should we adopt an “efficient reliability” screening process for socialized costs? • Should socialized solutions be put out to bid? • What are the roles of states, ISO, and FERC in all of the above?

More Related