190 likes | 380 Views
X-Ray Endstation Status. Stefan Moeller. Outline. Scope of X-Ray Endstation Systems (XES) Layout Status Milestones Plan for FY07 Budget and Staffing Summary. Scope and Goals.
E N D
X-Ray Endstation Status Stefan Moeller
Outline • Scope of X-Ray Endstation Systems (XES) • Layout • Status • Milestones • Plan for FY07 • Budget and Staffing • Summary
Scope and Goals • The X-Ray Endstation Systems (XES) group provides the infrastructure required for experimenters to make best scientific use of the LCLS radiation safely • XES equips a complete instrument for Atomic Physics Experiments • Coordinate all safety related aspects for the user environment and the experiments • Coordinate with the LUSI project
The Endstation Systems include: Infrastructure for LCLS Experiments: • Safety Systems • X-ray Personnel Protection System (PPS) • Laser Safety System (LSS) • Machine Protection System (MPS) • User safeguards • Controls • Network, data management and storage • High level applications • Laser timing system • Prototype Detector • New type of x-ray detector for LCLS experiments Instrumentation for first Atomic Physics experiments: • AMO chambers, sample source, detectors, optics, diagnostics • Beamline controls • Synchronized laser system Installation and Commissioning: • Integration with rest of LCLS and with LUSI Project
LCLS Photon Systems Photon System Manager J. Arthur Hal Tompkins X-Ray Transport &Diagnostics R. Bionta Science Advice J. Hastings X-Ray Endstation Systems S. Moeller Project Planning J. Doubrava Controls Bob Dalesio Mike Saleski (PPS) +7 FTE Mechanical Systems 2 FTE Lasers Bill White 2 FTE Detectors Niels van Bakel Atomic Physics John Bozek +1 FTE
Endstation Systems Location and Layout FEE, NEH, XR Tunnel, FEH: Controls, Cabling, Network, PPS, MPS NEH: AMO Instrument, Beamline Controls, Laser, Laser PPS FEE XR Tunnel 646 ft NEH FEH Interfaces: CF, XTOD, LCSL Controls, LUSI
Recent Developments: • Management: • XES Controls (1.6.2./2.6.2) Hamid Shoaee (CAM) • XES Laser Systems (1.6.4.) Bill White (CAM) • Scope changes: • Deleted streak camera • Transferred k-spectrometer to XTOD • Deleted laser amplifier of XES laser
XES Status • Updated and revised schedule of the entire 1.6/2.6 WBS • Revised estimate to complete (ETC) for all control accounts • Developed XES installation schedule • Cornell 2 D Detector • LDAC Review #3 for FY06 (July 19-20, 2006) • Good review, on schedule • Next review early 2007 • AMO Instrument • Developed scientific program with AMO science group • PRD draft • System Concept Review in November • Coordination with LUSI
XES Status (cont.) • Define requirements for PPS with Radiation Physics group. • PRD or Stoppers • Preparing PRD for k- spectrometer (LLNL) • Developed XES controls schedule • Fully integrated • Design started on AMO and 2D detector controls • Design starting on all systems
XES L3 Milestones FY08 CT: Controls PPS Complete 10/07 Award XES Laser System 10/07 2D Detector Production Start 11/07 CT: AMO Exp. Control Final Design Review 12/07 Network Installation Complete 3/08 Electron Dump Stoppers certified 3/08 Ready for Installation in NEH 4/08 AMO Mech./Vacuum Installation complete 5/08 CT: Controls Laser Timing System complete 5/08 Start XES Commissioning 9/08 XES Laser Operating in NEH 9/08 FY07 LDAC Mid-Project Review 2D Detector 3/07 CT: Network Final Design Review 4/07 CT: Timing Controls System Complete 5/07 CT: Cables and Racks Complete 5/07 CT: Laser Controls Systems Complete 7/07 XES Laser Final Design Review 8/07 FY09 Complete Acceptance Tests of Detectors 11/08 CT: AMO Exp. Control Complete 12/08
6 Month Look-ahead • XES Management: • Develop Commissioning Schedule • XES Controls: (LCLS Controls) • Identify staffing • Start design on all systems • Coordinate with LUSI • XES Laser: (LCLS Lasers) • Hire Laser Engineer (12/06) L4 • Specify Laser, Diagnostics and Transport (1-3/07) • AMOS: • PRD 11/06 • System Concept Review (1/07) L4 • Preliminary Design X1, Refocus Optics, Diagnostics, X2 (3/07)
6 Month Look-ahead (cont.) • K-Spectrometer: • PRD (11/06) L4 • PPS Stoppers and Shielding: • PRD (11/06) L4 • Design (12/06) • Prepare Bid (2/07) • Cornell Detector: • Proto #3 submission (10/06) • Diode submission (10/06) • Design Proto #4 (500px) (1/07) • Full lot prototype submission (2/07) L4
XES Cost/Schedule Variances • 1.6.7 AMO Design and Management • Cost overrun • Check rates • 1.6.8 Crystals and Gratings • Schedule delay – will catch up • PRD for k-spectrometer due end of Oct. • 2.6.5 2D x-ray Detector • Cost under run, on schedule • Actuals are lagging BCWS • Cost will catch up by the end of CY06 • 1.6.2 Controls • Slight schedule slip
XES Critical Path • Performed a critical path analysis • All tasks have several months of float • PPS System in Electron Dump ties into Commissioning of LINAC • Controlled by a L3 Interface Milestone
Summary Revised ETC and developed a new detailed schedule Budget and schedule is revalidated Design of AMOS Instrument is continuing 2D Detector program with Cornell is going well Starting on Laser System in early FY07 XES Controls: Start with design on all systems Coordinate with LCLS Laser, Controls and LUSI Coordinate safety for users