An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Request for Project InitiationPublic Safety Radio Modernization Assessment NM DOIT PCC Presentation March 27, 2013 Mike Neitzey

  2. Public Safety Radio Modernization Assessment: Vision • The existing LMR architecture is decades old and in dire needs of a comprehensive upgrade. • In conjunction with the build out of SIRCITS and narrow banding, this is an ideal time to pursue a comprehensive LMR modernization to provide operability and interoperability to meet local, state, federal needs and requirements.

  3. Assessment Components • 700MHz Spectrum Analysis • Capabilities Assessment • Needs Assessment and Gap Analysis • Plans

  4. 700MHz Spectrum Analysis • LTE Pilot: Approx. 7 sites in border area • CBP sites: Santa Theresa, Los Rios • State Police sites: Las Cruces, Deming • Little Florida and two “floating areas” • Several D-block sub-bands shared with Mexico • Need to assess any current use of channels before proceeding with pilot • Perform on-site frequency surveys/spectrum monitoring • Use for the LTE pilot project

  5. Capabilities Assessment • Review existing LMR capabilities • State agencies: NM DPS, NMDOT, NMDGF, NMCD, EMNRD, NMEMS, DHSEM • Local agencies • Albuquerque PD, Bernalillo Co. Sheriff/Emergency Mgmt/Consolidated Fire • Sandoval and Santa Fe Cos. Sheriff/Emergency Mgmt • Additional counties as needed: Eddy, Dona Ana, Luna, Otero, San Juan, and Socorro • Dispatch and site surveys, coverage analysis • Spectrum, capacity, interoperability assessment

  6. Needs Assessment & Gap Analysis • Conduct needs assessment interviews • State agencies • Local participants • Federal agencies • Perform gap analysis • Among agencies • Based on current capabilities • From unmet needs • Needs assessment will form basis of requirements for design task

  7. Plans • Identify goals, objectives, strategies, and actions to plan, budget, and implement improvement programs • Identify time-phased initiatives • Tied to specific prioritized objectives • To meet state and DoIT goals for public safety communications • That identify lead/responsible and participating departments and agencies • Support legislative budgeting process

  8. This request: • Release of $450K to secure professional services to: • Perform the 700MHz Spectrum Analysis ($47K) • Capabilities Assessment ($431K)

  9. Questions