Bond Construction Update Citizen’s Oversight Committee. Long Beach Community College District July 21, 2008. BUILDING TOMORROW TODAY. Agenda. Completed Construction Projects Current & Upcoming Construction Projects LAC South Quad Complex LAC Central Plant
E N D
Bond Construction UpdateCitizen’s Oversight Committee Long Beach Community College District July 21, 2008 BUILDING TOMORROW TODAY
Agenda • Completed Construction Projects • Current & Upcoming Construction Projects • LAC South Quad Complex • LAC Central Plant • LAC Learning Resources Center • LAC Building A, Student Services • LAC Math Technology Building • PCC Central Plant • PCC Learning Resources Center • PCC Industrial Tech Phase 1 • PCC MDAB (Multi-Disciplinary Academic Building) • LAC/PCC Building Needs Assessment Project • Toilet Improvement Projects • Quick-Start Projects • ADA Projects • Lighting Projects • Classroom Improvement Projects • Infrastructure Projects • Facilities Improvements • Q & A
Current and UpcomingConstruction Projects LAC Central Plant • Central Plant equipment, Public Safety, & Field house for Athletics • Installed (2) 600 ton Chillers and (1) 300 ton chiller with room for expansion • Installed 4 cooling towers with additional expansion space
Current and UpcomingConstruction Projects LAC Central Plant • Plant ready for operation and awaiting completion of SQC • Construction 96% Complete • Completion Anticipated Summer 2008
Current and UpcomingConstruction Projects Construction 70% Complete Adds 10,000 ASF to existing building Substantial Completion anticipated December 2008 LAC/Learning Resources Center
Current and UpcomingConstruction Projects Construction Approx. 62% Complete Space includes Approx. 68,000 ASF 32 modern classrooms and labs 38 faculty offices Executive office suites Multipurpose room State of the art Board Room Substantial Completion Anticipated December 2008 South Quad Complex
Current and UpcomingConstruction Projects Martinez Architects received Board Approval as the Architect of Record Programming work began on April 10, 2008 Completed Schematic Design (June 2008) Currently in Design Development phase Adds 4000 ASF to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. LAC Building A – Student Services Retrofit
Current and UpcomingConstruction Projects Marlene Imirzian & Associates Architects received Board Approval as the Architect of Record Will house Math and Culinary Arts instructional program as well as Reprographics LAC Math Technology Building
Current and UpcomingConstruction Projects Programming work began in May 2008 Completed Schematic Design (June 2008) Currently in Design Development phase FPP was approved by Board of Trustees and sent to state LAC Math Technology Building
Current and UpcomingConstruction Projects Currently completing Design Development Phase LAC Math Technology Building
Current and UpcomingConstruction Projects Houses Central Plant equipment and Maintenance and Operations facility Installed (3) 300 ton Chillers Installed 3 cooling towers Will support LRC Construction Approximately 67% Complete Completion Anticipated late Summer 2008 PCC Central Plant
Current and UpcomingConstruction Projects PCC Learning Resources Center • Construction 97% Complete • Modern Facility with Computer Lab and Multimedia • Stand alone Data Center. Provides District IT redundancy • Bridge to Bldg. EE • Design elements move towards energy efficiencies • Substantial Completion July 2008
Current and UpcomingConstruction Projects PCC Industrial Technology Center Phase 1 • Replaces Existing Antiquated Structures • Construction is 25% Complete • Modern Facility Houses Machine Tool and Welding Departments • New Northern Face of the Campus • Completion Anticipated Spring 2009
Current and UpcomingConstruction Projects PCC Multi-Disciplinary Academic Building (MDAB) • Programming is completed and submitted to the State for Approval • Completed Schematic Design and Design Development phase (June 2008) • Currently working on Construction Documents and Furniture Layouts • Anticipated start of construction Summer 2009 • Completed in Two phases
PCC - LRC and MDAB (Fly-By) p a c i f i c c o a s t
Current and UpcomingConstruction Projects LAC/PCC Building Needs Assessment Project • Restroom Improvement Projects • Quick-Start Projects • ADA Projects
Current and UpcomingConstruction Projects LAC/PCC Building Needs Assessment Project • Lighting Projects • Classroom Improvement Projects • Infrastructure Projects
Recently Completed Facilities Improvements Long Beach Community College District
Facilities ImprovementsLBCC Building “D” Planetarium Improvements • With the help of LBCC Foundation, funds were available to do the following: • carpet replacement • carpet added to the walls to ensure light-control for observational needs. • AC unit independent from the building HVAC system was added to serve the server room, for proper load ventilation. • New observation seats were installed. • entire room painted • new lighting installed. • Completed 06/2008
Facilities ImprovementsLBCC Building “J” Boiler Replacement • Replace existing boilers, pumps, expansion tanks and common flue with new equipment. • A newly upgraded design reflecting a mechanical engineered system was installed improving the efficiency of the boilers. This system is the main heating source serving the Auditorium. • Completed 06/2008
Facilities ImprovementsLBCC Building “B”, “C”, and “D” Roof Replacement • Replacement of roofs with a 30-year Garland roof materials • Removal of radio tower on Bldg “B” • Expected Completion 07/2008
Facilities ImprovementsLBCC ERD Tenant Improvements and Relocation • Economic Resource Development • Complete build out of two-hard walled offices, a kitchenette, and a server room • Relocation of a 4,000sq. ft. office space into the newly re-designed 3,000sq ft. office space • New modular cubicle work stations were adapted and installed • Completed 05/2008
Facilities ImprovementsLBCC Important Ongoing Initiatives • Building Needs Assessment Project • Parking Structure/Traffic Study • Master Landscape Project • District Wide Energy Efficiency Improvements • Electronic Signage • Wayfaring and Building Signage • Facilities Website • Facilities Work Order System • Buildings M & N Replacement at LAC • Building G at PCC • Modernization of Building P at LAC (IPP) • Replacement of Building M (Construction Trades) at PCC (IPP)
QUESTIONS & ANSWERS BUILDING TOMORROW TODAY