Bond Construction Update Facilities Advisory Committee Long Beach Community College District February 2, 2011 EDUCATE ENGAGE EMPOWER
Agenda • Completed Construction Projects • District Wide – Electronic Signage Plan • Current Construction Projects • LAC Building A – Student Services Retrofit • LAC Parking Structure • LAC Building O Complex • LAC Infrastructure Improvements Project and District Wide – Energy Efficiency Project • LAC Building I (Bookstore) • LAC South Walkway Extension • PCC MDAB (Multi-Disciplinary Academic Building) • PCC Walnut Ave. Arrival Court • District Wide – Monument Signs • Upcoming Construction Projects • LAC W Trailers Demo • PCC Building CC Retrofit • Q & A
Completed Construction Projects District Wide – Electronic Signage Plan Measure E 2008 • District Wide Signage Plan complete for LAC & PCC • Construction completed Fall 2010
Current Construction Projects LAC Building A – Student Services Retrofit Measure E 2008 • Adds 6,500 Sq. Ft. to existing building • Notice To Proceed given to SMC Construction on 12/29/10 • Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. • End of construction anticipated Summer 2012
Current Construction Projects LAC Parking Structure – Measure E 2008 • Spaces for 900 Vehicles • Finalizing installation of solar arrays, irrigation, signage, and data/telecom runs • Anticipated end of Construction Spring 2011
Current Construction Projects LAC Building O Complex – Measure E 2008 • Two structures totaling 87,000 square feet • Occupants for Building O2 are Foundation, ERD, tenants, and ALCI (soon to come) • Occupants for Building O1 will be IITS, BMT, and Warehouse Facility • Anticipated completion February 2011
Current Construction Projects LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E 2008 • Total annual estimated savings of 1.5 mil. Kwh • Project started Fall 2009; currently working on phase 6 (partial), 7, 8A, 9A (Landscape),and 10 (G and H Quad area) • Majority of existing building HVAC systems to be upgraded and connected to the Central Plant • Buildings G & H are connected • Buildings B, C, D, E, and J will be scheduled in the next couple months • Exterior lighting and controls upgrades • All parking lots north of Lew Davis are on new system • New Reclaimed Water tie-ins to irrigation still to come • New gas lines installed for Buildings B, C, D, E, G, H, J, M, N, and P • New domestic lines installed for Buildings B, C, D, E, F, G, H, I Trailers, J, K,L, M, N, P • Anticipated end of construction Winter 2011
Current Construction Projects LAC Building I - Measure E 2008 • Adds additional 4,000 square feet to existing building • Architecture to match LAC Mediterranean Theme • Notice To Proceed given to G2K Construction on 11/15/10 • End of Construction anticipated Fall 2011
Current Construction Projects LAC South Walkway Extension Measure E 2008 • 99% complete • Currently going through final punch-list • Continues Master Plan pedestrian corridor
Current Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2002 and 2008 • Notice To Proceed issued on 7/29/10 • Currently in phase 1 of construction (DD and EE in construction) • Portables for swing space installed Summer 2010 complete and occupied (MD Trailers) • Project to be completed in two phases – estimated completion for DD and EE is Summer 2012
Current Construction Projects PCC Walnut Ave. Arrival Court - Measure E 2008 • UU/VV demo completed • Currently grading site • Site to be converted to a parking lot • Estimated end of construction Spring 2011
Current Construction Projects District Wide – Monument Signs Measure E 2008 • District Wide Monument Signs. • Locations: • LAC-Clark/Conant – installed January 8, 2011 • PCC-20th/Walnut Ave. – installation still to come • Installation of building designators for LAC Bldg. O1 and O2 completed • Estimated construction completion Spring 2011 LAC Monument Sign LAC Bldg. Designator PCC Monument Sign
Upcoming Construction Projects LAC W Trailers Demo - Measure E 2008 • Design for site completed • W Trailers to be demolished • Site to be converted to a parking lot and a bio-swale • Board of Trustees approved on 1/18/11 to Green Giant • Notice to Proceed to be issued once docs have been submitted by contractor
Upcoming Construction Projects PCC Building CC Retrofit - Measure E 2008 • Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices • Swing space located on PCC Campus (Bldg. GG) • Approved by DSA on 1/27/11. Bid process to commence shortly • To be completed concurrently with MDAB project phase 1 • Anticipated end of construction 2012
Liberal Arts Campus Site Plan l i b e r a l a r t s
Pacific Coast Campus Site Plan p a c i f i c c o a s t
QUESTIONS& ANSWERS EDUCATE ENGAGE EMPOWER