1 / 12

Petroleum Engineering 626 Offshore Drilling Lesson 6C Motion Compensation

Petroleum Engineering 626 Offshore Drilling Lesson 6C Motion Compensation. Lesson 6C - Motion Compensation. Bumper Subs T = H - wd Buoyant Riser Jackup Rig. Bumper Subs.

gautam
Download Presentation

Petroleum Engineering 626 Offshore Drilling Lesson 6C Motion Compensation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Petroleum Engineering 626Offshore DrillingLesson 6C Motion Compensation

  2. Lesson 6C - Motion Compensation Bumper Subs T = H - wd Buoyant Riser Jackup Rig

  3. Bumper Subs Fit into the drill collar string, but do not have the ruggedness of drill collars. To obtain a reasonable operating life from bumper subs, action has to be taken on the following points of concern: 1. Always run the bumper subs at the neutral point in the string.

  4. Bumper Subs, cont’d 2. Bumper subs are designed to stroke, and if operated at a single position, they will wear at that position. 3. Running the subs in tension minimizes the area through which the torque will be transmitted, and will cause excessive wear and fatigue.

  5. Bumper Subs 4. Running the joint in compression increases torque reversals and fatigue in the tool. It also increases “bit chatter” and instantaneous peak torque, causing unnecessary wear to the tool and the string. This is the fault of the operation, not the sub.

  6. Bumper Subs 5. From items 3 and 4 above, it is evident that once the string has been run, the weight on the bit is fixed. This weight should not be changed until the string has been pulled and the number of drill collars below the bumper sub changed.

  7. Bumper Subs 6.Do not separate the bumper subs in a drillstring for heavy drilling operations. 7.Special care and maintenance are required to obtain a reasonable operating life. *Remember: bumper subs fit into the same part of the drillstring where drill collars and stabilizers have been destroyed. This is a severe test of workmanship &maintenance.

  8. Unbalanced Bumper Subs

  9. Buoyant Riser Module

  10. Cantilever Jackup Rig Float out to location Then lower legs to seafloor Then jack up

  11. Jackup Rig Side View

  12. Jackup Rig Deck Plan