An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MMS Update for TPTF February 6, 2008Murray NixonSai Moorty (via phone) http://nodal.ercot.com 1

  2. Agenda • MMS schedule • Deferral key driver (reminder) • Proposed deferrals update • MMS2 FAT status • MMS3 pre-FAT status http://nodal.ercot.com 2

  3. MMS Release Schedule http://nodal.ercot.com 3

  4. Key Driver for Proposed Deferrals • Ensure the final MMS FAT completes by 30Jun08, allowing 2 months for integration & EDS4 activities prior to the 168 hour test start on 1Sep08 • This was the direction provided to the ERCOT & ABB MMS teams by the Nodal and ABB executives on 28Nov07 • The proposed deferrals will help MMS meet the Nodal program timeline http://nodal.ercot.com 4

  5. Proposed Deferrals Update http://nodal.ercot.com 5

  6. Proposed Deferrals Update (cont’d) http://nodal.ercot.com 6

  7. MMS2 FAT Status • MMS2 FAT started on 3Dec07 with a targeted completion of 11Jan08 • FAT completed on 25Jan08; 2 week delay allowed correction and retesting of all severity 1 and 2 defects • 555 structured tests completed with an 89% pass rate • All severity 1 & 2 defects from other Nodal projects were reviewed; MMS team and defect originator(s) determined that all were: 1) part of a future release, 2) fixed and successfully re-tested, or 3) reclassified • MMS2 now deployed to various downstream systems (e.g., EDS, EIP, INT) http://nodal.ercot.com 7

  8. MMS3 pre-FAT Status • MMS3 pre-FAT started on 4Feb08 with a targeted completion of 15Feb08 • MMS3 is comprised of 159 structured tests • At the end of day 2 of testing, 59 tests were complete with a 97% pass rate • 33 defects have been identified; no sev 1 or sev 2 http://nodal.ercot.com 8