1 / 21

Seneca Pumped Storage Generation Plant

Asia-Pacific Partnership . on. Clean Development and Climate. Seneca Pumped Storage Generation Plant. Asia Pacific Partnership United States of America Power Generation Task Force August 13 – 17, 2007. Governor and Unit Control Upgrades & Outage Planning. Ron Kovach/Tom Groff.

geneva
Download Presentation

Seneca Pumped Storage Generation Plant

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Asia-Pacific Partnership on Clean Development and Climate Seneca Pumped Storage Generation Plant Asia Pacific PartnershipUnited States of AmericaPower Generation Task ForceAugust 13 – 17, 2007 Governor and Unit Control Upgrades & Outage Planning Ron Kovach/Tom Groff

  2. Phase I Governor Retrofit Units 1,2 & 3 Spring 2006 • Original Governors – Woodward 1960’s vintage. • Installation was during a 3 week outage. Seneca Pumped Storage Generation Plant 2

  3. Original Control Panel Seneca Pumped Storage Generation Plant 3

  4. Original Mechanism Seneca Pumped Storage Generation Plant 4

  5. Original Mechanism Seneca Pumped Storage Generation Plant 5

  6. Retrofit – Units 1,2,3 • Contracted with L&S Electric for New Hardware/Software • Installed Allen-Bradley Control Logix PLC Seneca Pumped Storage Generation Plant 6

  7. New Control Panel Seneca Pumped Storage Generation Plant 7

  8. New Mechanism Seneca Pumped Storage Generation Plant 8

  9. New Mechanism Seneca Pumped Storage Generation Plant 9

  10. Phase II Unit Control Retrofit Units 1,2 & 3Spring 2007 • Original Equipment, 1960’s vintage • Hardwired operator panel and relays • Becoming Obsolete and Unreliable • Installation was during a 3 week plant outage • Remote I/O panel were pre-installed Seneca Pumped Storage Generation Plant 10

  11. Original Control BenchBoard Seneca Pumped Storage Generation Plant 11

  12. Rear View Seneca Pumped Storage Generation Plant 12

  13. Removal Seneca Pumped Storage Generation Plant 13

  14. What do we do now? Seneca Pumped Storage Generation Plant 14

  15. Installation Remote Input/Output Panel Installed Remote I/O panels on each unit. Communication to main unit processors is with new fiber optic cables. This reduced wiring and labor cost and prevents electrical signal noise. Seneca Pumped Storage Generation Plant 15

  16. Upper Reservoir Remote Panel Installed a new Fiber Optic cable from Upper Reservoir to Plant Controllers. This provides a more reliable means of reservoir level monitoring and control. Seneca Pumped Storage Generation Plant 16

  17. Installation • L&S Electric supplied all hardware/software and programming • Installed Allen-Bradley Controllogix processors. • Installed iFIX HMI software for the operator stations. Seneca Pumped Storage Generation Plant 17

  18. New panel fronts with a redundant Operator Interface Panel Seneca Pumped Storage Generation Plant 18

  19. New Rear View Seneca Pumped Storage Generation Plant 19

  20. New Operator Station Seneca Pumped Storage Generation Plant 20

  21. Outage Planning Depending on the size and complexity of the work planning starts from 6 to 24 months before the outage. Create work packages. Identify equipment, material and services needs. Project funding, duration and timing are locked in. Outage start and end dates are set. Create purchase orders, bid specifications, etc. and release. Working with the appropriate parties create schedules (individual project and overall outage) and determine staffing levels. Identify the critical path. Perform cost/benefit analysis of ending outage early vs. use of premium time Evaluate staffing options. How many days/week, hours/day. • DURING THE OUTAGE • Daily • “All Hands” meeting at the beginning of each shift. • Process time sheets and invoices • Weekly • Meeting to formally review progress and budget with Director • Periodically • Assess outage for staffing changes Schedule locked in approximately one month in advance of outage start date. Outage Starts Seneca Pumped Storage Generation Plant 20

More Related