Transmission Transparency Project. Project Plan The Hague, 13 December 2007. Contact: Oliver Altenhoff E.ON Gastransport AG & Co. KG Kallenbergstr. 5 45141 Essen GERMANY Oliver.altenhoff@eon-gastransport.com. Overview. Introduction Information to be published
E N D
Transmission Transparency Project Project Plan The Hague, 13 December 2007 Contact: Oliver Altenhoff E.ON Gastransport AG & Co. KG Kallenbergstr. 5 45141 Essen GERMANY Oliver.altenhoff@eon-gastransport.com Transmission Transparency, 13.12.2007
Overview • Introduction • Information to be published • List of Participating Operators • Interconnection Points • Time Schedule • Specific Time Schedule of Implementation • Monitoring of Implementation • Cost Statements Transmission Transparency, 13.12.2007
Introduction • At SG meeting in Dublin, TSOs announced the development of a project plan for best practices based on requests of market participants • EFET wish list established (Requirements go beyond current legislative requirements) • Transparency questionnaire responses and Ofgem-Workshop • A high-level plan published by TSO: commitment to the wish list • Detailled plan shows the implementation process Transmission Transparency, 13.12.2007
Information to be published • The following information refers to Interconnection Points • Max technical capacity of the transmission system • Daily commercial firm and interruptible capacity • Interruptions /Interrupted flows • Daily flow / aggregated allocations (D+1) • Daily prompt allocation information to each shipper • Daily aggregate day-ahead nominations (D-1) • Historic gas flow information database Transmission Transparency, 13.12.2007
List of Participating Operators Denmark France Ireland Netherlands Germany Belgium Sweden United Kingdom Northern Ireland Transmission Transparency, 13.12.2007
Interconnection Points 69 points publ. avbl. 57 points confid. Transmission Transparency, 13.12.2007
Time Schedule First wins Later wins Final wins Transmission Transparency, 13.12.2007
Specific Time Schedule of Implementation Transmission Transparency, 13.12.2007
Specific Time Schedule of Implementation Transmission Transparency, 13.12.2007
Monitoring of Implementation • TSO will send progress reports to RCC • First progress report in May 2008 • Mid-term report in February 2008 • Second progress report in November 2008 • Mid-term report in July 2008 • Final progress report in January 2009 Transmission Transparency, 13.12.2007
Cost statements • Operators will have first cost estimations in Jan/Febr. 2008 for discussion with RCC. • Should be handled on the national level first Transmission Transparency, 13.12.2007
Transmission Transparency Project Thank you! Contact: Oliver Altenhoff E.ON Gastransport AG & Co. KG Kallenbergstr. 5 45141 Essen GERMANY Oliver.altenhoff@eon-gastransport.com Transmission Transparency, 13.12.2007