310 likes | 486 Views
NYWEA 2013 Water for the Future. Supply Augmentation Need Planning Mark N. Page, Jr. September 19, 2013. Agenda. Background on Water for the Future Current Program Modeling Results. Water Supply System Overview. Above Kensico Reservoir Rondout - West Branch Tunnel (Delaware Aqueduct)
E N D
NYWEA 2013 Water for the Future Supply Augmentation Need Planning Mark N. Page, Jr. September 19, 2013
Agenda • Background on Water for the Future • Current Program • Modeling Results
Above Kensico Reservoir Rondout - West Branch Tunnel (Delaware Aqueduct) West Branch – Kensico Tunnel (Delaware Aqueduct) Ashokan – Kensico Reach (Catskill Aqueduct) Rondout Reservoir Ashokan Reservoir Below Kensico Reservoir Kensico Reservoir and Connecting Tunnels to Eastview Hillview Reservoir City Tunnels #1 & #2 Catskill & Delaware Aqueducts between Kensico and Hillview Reservoirs Richmond Tunnel (Brooklyn to Staten Island) Dependability Program 10 Critical Areas Have No ‘Back-up’ Infrastructure or Supplies
Dependability Supply Needs Above Kensico Ashokan Reservoir (35 - 135 MGD) Ashokan Kensico Reach (35 - 135 MGD) Rondout Reservoir (335 - 435 MGD) Rondout-West Branch Tunnel (335 - 435 MGD) West Branch Kensico Tunnel (385 - 485 MGD)
2007 RWBT Identified as Primary Area of Concern RWBT conveys Delaware system water and is the primary source for Towns of Newburgh and Marlborough and approximately 50% of New York City’s supply
RosetonLeakage Project Background - Roseton Surface Expression A dozen or so surface expressions Flow observed on west bank of Hudson River Testing program and analysis estimates leakage of 15 to 35 mgd.
2007 Shutdown Schedule How Long will the Tunnel be Out of Service?
Increase Aqueduct Capacities Croton Pump Stations Potential Solutions for Dependability Parallel Tunnels Abandoned Sources (Westchester Co.) Hudson River and Harbor Surface Water, Hudson Groundwater Interconnections Expand Groundwater Use Demand Reduction
Augmentation Project Screening Project Tiering/Prioritization – Focuses Effort on Best Projects and Combinations
Delaware Repair: Alternative water sources • Project evaluation to identify a group of projects to meet NYC’s alternate water supply needs (2008) • Factors: • Cost • Schedule • DEP Control 26 Projects • Key: • Redundant tunnels • Optimization of existing system • Groundwater • Desalinization of Hudson River or Harbor water • Interconnections to New Jersey or Connecticut 39 Projects
Delaware Repair: Alternative water sources • Top 26 Projects falls to 17 with the removal of mutually exclusive projects.
Moving to Design • In 2008 and 2009 DEP hired new consultant team to develop parallel tunnel and bypass tunnel concepts to address the RWBT leaks
Repair of the Leaks Shaft 6 Tunnel Unwatering Shaft Shaft 2A 17 Shaft 9 Rondout Reservoir Shaft 8 Shaft 2 EL 840 Shaft 1 Shaft 5A Shaft 5 Shawangunk Mountains Shaft 4 Shaft 7 West Branch Reservoir Rondout Creek Walkill River Shaft 3 Hudson River El 503 El -600.0 Wawarsing • Roseton Repairs • Not possible from within tunnel • Access requires new shafts • Best Solution is Bypass Roseton • Wawarsing Repairs: • Possible from within tunnel • Access via Shaft 2A • Confinement Relatively good
Recent Modeling In 2010 DEP shifted from evaluating a full repair of the RWBT to constructing a bypass around the leak in Roston, NY This bypass included the use of inundation plugs to handle tunnel inundation, resulting in approximately a month shutdown period for the connection
OST Supply Curve (2012-02-01) OSTv1.3.7.1_Aug-SC_000 Runs were conducted for these four supply levels
Threshold Approach - Objectives • Objectives (during an outage): • Provide advance notice of potential shortfall conditions • Provide DEP with enough time to take some preventive action • Objectives (now, during the planning process): • Accurately simulate operations during an outage • Provide a fuller picture of how various augmentation projects perform • Provide a framework to help support DEP’s risk analysis • Uncertainties in augmentation project capacity • Uncertainties in RWB repair duration
Big Break Through!!! • Inundation Plugs not necessary!!! • This resulted in the following: • A shorter shutdown period for the connection of approximately10 months • A phased connection of the bypass tunnel to the RWBT • Allowed for an evaluation of shorter shutdown periods and bailout contingencies • We evaluated four phased approaches: • Fixed Staging • 4 month / 3 month / 3 month • 5/5 • 6/4 • Variable Stage (10 months total but can be broken and phased over 3 years)
Recent Modeling Results Where we are now!
Water Demand and Dry Weather Wastewater Flows Historic Flows and Future Projections 2012
Water Supply System Augmentation and Improvement Conservation / Demand Management Upper Catskill Aqueduct Optimization Queens Groundwater Rehabilitation
Modeling Results End of 2012 • As a result of three workshops, extensive modeling, and shutdown design updates: • Variable Stage Shutdown allows for complete shutdown in one phase • Includes a repair starton Oct 1 with augmentation starting June 1 • Provides for a singular phase repair based on modeling using forecasted 60 day look ahead for continuation of shutdown or bailout from repair • Provides for allowance for remaining repair to be completed in subsequent years, if necessary • 58 mgd of augmentation (33 mgdGroundwater + 25 mgd Demand Management) • Catskill Aqueduct maximum flow increased to 636 mgd via Catskill Rehabilitation Project • Croton WFP flow at 250 mgd to account for diurnal demand pattern.
Outage Surface Plot: Variable Outage Most outages start in October Substantially longer Stage 1 outage duration with 10% reserve and CAT 636
Likelihood of Completion: Variable Staging Likelihood of Completing x Outage Days • Shows probability of successfully completing the variable stage shutdown repair during a three consecutive year period • Allows for three chances to complete the 10 month (300 day) repair • Could complete entire 10 months in first year • Or could complete remaining repair period during subsequent one or two years if insufficient supply is available in first year • Fixed stage shutdowns do not allow for this flexibility since entire three year period is required for each repair period • 4 lines for each color – these represent: • NCA 250 / Demand Pattern • NCA 290 / Demand Pattern • NCA 250 / Demand Regression • NCA 290 / Demand Regression This plot shows the likelihood of completing 300 total outage days over a period of up to 3 years.
Likelihood of Completion: Summary Table 99% Probability of Success!
Next Steps • Continue refining shutdown design and modeling • Continue thinking about issues that could arise • Develop operational plans for shutdown