110 likes | 221 Views
30 MW Webberville Solar Plan Update. Hosted By: Gemini Solar – John Street Village of Webberville – Hector Gonzales, Mayor Austin Energy – Ed Clark October 1, 2009, 7:00 p.m. Pavilion at East Metro Park. 30 MW Webberville Solar Project. Largest crystalline solar PV Project in U.S.
E N D
30 MW WebbervilleSolar Plan Update Hosted By: Gemini Solar – John StreetVillage of Webberville – Hector Gonzales, Mayor Austin Energy – Ed Clark October 1, 2009, 7:00 p.m.Pavilion at East Metro Park
30 MW Webberville Solar Project • Largest crystalline solar PV Project in U.S. • 350-400 acre footprint • 130,000 solar panels • AE buying all power for 25-year term • Gemini will build, own and operate facility
30 MW Webberville Solar Project PRELIMINARY PRELIMINARY PRELIMINARY
30 MW Webberville Solar Project • Signed Contract – August 2009 • Environmental Assessment – Ongoing • ERCOT interconnection review ongoing • Selection of Contractor – Oct/Nov • Design and Site preparation – Start Nov/Dec • Project Construction – Start Spring 2010
30 MW Webberville Solar Project • Project about 600 construction jobs • General Contractor Responsible for job Recruiting • Point of contact to be established • Site preparation, electrical, assembly/installation • Two-full time positions for operations
30 MW Webberville Solar Project • Hours of Operation • Construction Traffic Plan • Security / Safety • Fencing • Landscaping
30 MW Webberville Solar Project • Observation deck • School tours • Industry tours • Economic Development
30 MW Webberville Solar Project Questions