30 MW Webberville Solar Plan Update

30 MW Webberville Solar Plan Update. Hosted By: Gemini Solar – John Street Village of Webberville – Hector Gonzales, Mayor Austin Energy – Ed Clark October 1, 2009, 7:00 p.m. Pavilion at East Metro Park. 30 MW Webberville Solar Project. Largest crystalline solar PV Project in U.S.

haig
Download Presentation

30 MW Webberville Solar Plan Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 30 MW WebbervilleSolar Plan Update Hosted By: Gemini Solar – John StreetVillage of Webberville – Hector Gonzales, Mayor Austin Energy – Ed Clark October 1, 2009, 7:00 p.m.Pavilion at East Metro Park

  2. 30 MW Webberville Solar Project • Largest crystalline solar PV Project in U.S. • 350-400 acre footprint • 130,000 solar panels • AE buying all power for 25-year term • Gemini will build, own and operate facility

  3. 30 MW Webberville Solar Project PRELIMINARY PRELIMINARY PRELIMINARY

  4. 30 MW Webberville Solar Project • Signed Contract – August 2009 • Environmental Assessment – Ongoing • ERCOT interconnection review ongoing • Selection of Contractor – Oct/Nov • Design and Site preparation – Start Nov/Dec • Project Construction – Start Spring 2010

  5. 30 MW Webberville Solar Project • Project about 600 construction jobs • General Contractor Responsible for job Recruiting • Point of contact to be established • Site preparation, electrical, assembly/installation • Two-full time positions for operations

  6. 30 MW Webberville Solar Project • Hours of Operation • Construction Traffic Plan • Security / Safety • Fencing • Landscaping

  7. 30 MW Webberville Solar Project • Observation deck • School tours • Industry tours • Economic Development

  8. 30 MW Webberville Solar Project Questions