1 / 5

September 18, 2007 Regional Disturbance

Summary of a violent storm event on September 18, 2007, which caused transmission line outages and electrical separation in the Midwest and Eastern Interconnection. Challenges in real-time operations and fault scenarios are discussed.

hbollinger
Download Presentation

September 18, 2007 Regional Disturbance

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. September 18, 2007Regional Disturbance PSERC Project Proposal

  2. Event Summary • Violent storms moving through the Dakotas and Minnesota early on September 18 forced numerous transmission lines (mainly 345 kV) out of service. • As a result, at about 6:20 am EDT, a large portion of the western Midwest Independent Transmission System Operator (MISO) system along with systems in Manitoba and Saskatchewan separated electrically from the rest of the Eastern Interconnection. • MISO was able to restore the U.S. section of the grid within 10 minutes, and remained in conservative operation until the grid was stabilized and secure as a precaution. • Saskatchewan Power also separated from the Eastern Interconnection when it lost its 230 kV tie lines into Manitoba and North Dakota. Generation outages totaling 896 MW occurred as well, resulting in customer outages. Saskatchewan Power reconnected to grid within an hour, and almost all customer load was restored within 2 hours.

  3. Rough Sketch of Island

  4. Challenges in Real Time Operations • There is a need to identify current system margin from transient instability following a disturbance/fault: Current On-Line Transient Stability Assessment typically is setup where: • A real time snapshot is taken from State Estimator • The State Estimator Solution is solved in an off-line powerflow application • And then transient stability analysis is performed using off line software such as PSS/E Dynamic or Power Tech TSAT for given fault scenarios. This approach requires large detailed modeling data for generators, load, and relays. This approach requires “scenario of faults” are pre-determined. This approach can also be time consuming and not viable in the real time operations

  5. Challenges in Real Time Operations • Detail Challenges in the model: • MISO has a large EMS model that encompass almost all Eastern Interconnection. Creating a conventional dynamic model is not practical. The previously mentioned approach would require a good method of equivalencing. • Challenges in determining fault scenario (i.e. Fault Screening): • In the Sep 18 event, N-2 contingencies are the initiators of the event. The two line trips do not share any commonality (i.e. they are not common towers, not common breakers, not common right of way, etc)

More Related