1 / 11

Module to Disc Assembly

Module to Disc Assembly. Infrastructure Services and test box Evaporative cooling system Disc Handling Tests on disc 9 Redundancy link results Cooling performance Current Inventory Future plans. Infrastructure. Services and test box Optical Fibres and DCS in place

henry
Download Presentation

Module to Disc Assembly

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Module to Disc Assembly • Infrastructure • Services and test box • Evaporative cooling system • Disc Handling • Tests on disc 9 • Redundancy link results • Cooling performance • Current Inventory • Future plans UK-V RAL 8th September 2004

  2. Infrastructure • Services and test box • Optical Fibres and DCS in place • Test cables terminate in patch panels allowing the connection to PPF0 through a short length of ribbon cable • Test box is equipped with simple removable aluminium covers front and back UK-V RAL 8th September 2004

  3. Evaporative cooling system • 4 heat exchangers have been constructed • Pipe-work, valves and distribution blocks have been installed • Connections are made using flexible stainless steel pipe-work • Leak testing is very time consuming! UK-V RAL 8th September 2004

  4. Disc Handling • The disc handling jig using the crane has been modified to optimise the smooth attachment and removal of discs for both the mounting tooling and the test box • Further modification will be required for transferring the disc to and from the tooling to mount the disc in the end-cap cylinder UK-V RAL 8th September 2004

  5. Redundancy Link Results • The inclusion of the redundancy links on disc 9 introduced additional noise • Investigations identified the following improvements • Replacement of a 5kW resistor in the ground line with 0W • An improvement in the redundancy link grounding • For a full report see http://hep.ph.liv.ac.uk/~ashley/Disk9_results_050804.pdf UK-V RAL 8th September 2004

  6. Extracts from the report UK-V RAL 8th September 2004

  7. Results with 0W resistor + new links still show a distortion at~ 0.3 fC Occupancies look OK UK-V RAL 8th September 2004

  8. Cooling Performance • The cooling system tests have involved running the Cold Room with a low dew point (<-25C) but operating at room temperature • Test box is flushed with dry air • The evaporative cooling for Disc 9 was turned on quadrant by quadrant (no power load) • Each quadrant will cool down to –25C but when all four operate together one quadrant was not cooled efficiently • The suspect heat exchanger has been replaced • All quadrants now cool together to –25C • Need to check performance with power on all quadrants UK-V RAL 8th September 2004

  9. One problem is that the programmed switch-off mode for the cooling rig allows the temperature to fall to –40C • Simple cure is to enter the cold room very briefly and close valves feeding the disk • Can also investigate possibility of modifying the code in the controller • 8 Hybrids and 4 modules were mounted without thermal grease, powered and clocked with ambient temperature of ~20C • the hybrids temperatures varied between 6C and 13C (Ambient in test box ~ +10C) • Hybrids ran cooler ~ 6C-8C, modules at ~12C-13C • Modules with grease run ~ 5C cooler (ambient ~ 20C) UK-V RAL 8th September 2004

  10. Current Inventory • Disc 9C has been accepted and is in use • Disc 8C has arrived and is awaiting acceptance tests • Disc 7C is expected next week • In terms of modules we currently have in Liverpool • 171 (Good + Pass) outer modules • 76 (Good + Pass) Middle modules • 15 Outers and 29 Middles being processed UK-V RAL 8th September 2004

  11. Future Plans • There is a proposal to mount the least good modules on Disk 9 (~10 bad channels) • Next step is to mount all the lower modules using correct tooling and thermal grease • Electronic characterisation • Thermal tests with thermal camera • Mount the remaining modules and characterise a completed disc • In parallel perform acceptance tests on discs 8 and 7 UK-V RAL 8th September 2004

More Related