An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FAIR Status

    Overview KHuK, Bad Honnef, 6/12/13
  2. Facility for Antiproton & Ion Research Nuclear Structure & Astrophysics (Rare-isotope beams) Hadron Physics (Stored andcooled 14 GeV/c anti-protons) SIS18 p-Linac SIS100/300 UNILAC QCD-Phase Diagram (HI beams 2 to 45 GeV/u) HESR Rare-Isotope Production Target Fundamental Symmetries & Ultra-High EM Fields (Antiprotons & highly stripped ions) Anti-Proton Production Target Dense Bulk Plasmas (Ion-beam bunchcompression & petawatt-laser) CR &RESR Cryring NESR Materials Science & Radiation Biology (Ion & antiproton beams) 100 m Accelerator Physics KHuK, Bad Honnef, 6/12/13
  3. FAIR Partner Issues Member States / Shareholders After all memberstateshavenotified the German Foreign Office, the FAIR Conventionwill comeintoforceunder international law. This will happen verysoon! Associatemembers UK (STFC) Associate Member sincesummer 2013 Talks withSaudi Arabiaongoing Partners DiscussionswithSpainongoing DiscussionswithItalyongoing Interestedparties Talks withscientistsfromThe Netherlands Talks withscientistsfromNorway Talks withscientists/Academy of Sciences of China Talks withscientists/Academy of Sciences/State Agency of Science, Innovation andInformatization of Ukraine Talks withscientists/researchcouncil in Brazil Talks withscientists/National Science & Technology Commission (to the president) of South Korea Talks withscientists in Japan Talks withscientists in Turkey Talks withscientists in the USA Talks withESA Operation costsatruntime 2020 needtobeagreed upon KHuK, Bad Honnef, 6/12/13
  4. MSV’sFunding Civil Construction – cash contributions only 400 M€ in 2005 prices Shared between Germany and other FAIR Member States Completely funded Accelerators – mostly in-kind contributions Costs defined by Cost Book In total 382 M€ (2005 prices) Completely funded Experiments – mostly in-kind contributions Only 1/3 funded by FAIR 2/3 still to be found Additional funding by shareholders outside FAIR budget New FAIR members/associates Funding by third parties Organised and agreed upon via Resources Review Boards, one for each of the 4 large collaborations Overall total = 1027 M€ at 2005 price level KHuK, Bad Honnef, 6/12/13
  5. Civil Construction Synchrotrons: 1.1 km HESR: 0.6 km With beamlines: 3.2 km Existing SIS 18 Total area > 200 000 m2 Area buildings ~ 98 000 m2 Usable area ~ 135 000 m2 Volume of buildings ~ 1 049 000 m3 Substructure:~ 1500 pillars, up to 65 m deep KHuK, Bad Honnef, 6/12/13
  6. ...with complex interior Central Switchyard Building 36 m down in the ground KHuK, Bad Honnef, 6/12/13
  7. Google Maps KHuK, Bad Honnef, 6/12/13
  8. ...closing in KHuK, Bad Honnef, 6/12/13
  9. Civil Construction Timeline KHuK, Bad Honnef, 6/12/13
  10. Accelerator Challenges Compact & cost effective accelerators Fast cycling superconducting magnetsdB/dt~ 4T/s Precision beams Electron & stochastic cooling XHV @ high beam intensities Extremely high vacuum ~10-13mbar Fast acceleration High gradient, variable frequencyFerrite & MA loaded cavities KHuK, Bad Honnef, 6/12/13
  11. HESR Prototyping & Tests at COSY Pellet Target WASA Residual Gas Profile Monitor Barrier Bucket Cavity Stochastic Cooling 2 MeVe-Cooler KHuK, Bad Honnef, 6/12/13
  12. FAIR Experiments CBM APPA Super-FRS PANDA NuSTAR KHuK, Bad Honnef, 6/12/13
  13. Technical Progress Experiments Technical Design Reports Required by most funding agencies; update as of 3 Dec 2013: In preparation 3rd meeting of Expert Committee Experiments, ECE: 7 Jan. 2014 2nd meetings of Resources Review Boards: 4-5 Feb. 2014 Implement links for common timelines for all experiments Cost Book update to accommodate MSV changes in progress Construction Memoranda of Understanding 2014/15 KHuK, Bad Honnef, 6/12/13
  14. Overall Funding Experiments Cost estimate 2013 243 M€ = 193 M€ in 2005 prices Cost Book (issued in 2006) 188 M€ in 2005 prices Breakdown (2005 prices) FAIR’s budget: 63.9 M€ In-Kind Contract: 6.0 M€ Collab. Contract: 1.2 M€ Nov 2013: additional 2.8 M€ To be contracted: 5.2 M€ Other approved funding: 46.6 M€ Expressions of Interest: 45.7 M€ To be assigned: 36.4 M€ KHuK, Bad Honnef, 6/12/13
  15. ...by Collaboration KHuK, Bad Honnef, 6/12/13
  16. Roadmap Experiments KHuK, Bad Honnef, 6/12/13
  17. Timeline MSV 2011 2012 2013 2014 2015 2016 2017 2018 2019 12 9 11 6 7 8 10 Submission of construction applications Start Site preparation First civil construction contracts Building of accelerator & detector components Partially finishing civil construction work Start installing & commissioning accelerator and detector components Start commissioning with beam 10 6 7 12 8 9 11 KHuK, Bad Honnef, 6/12/13
  18. Operation Cost at Runtime 2020 Numbers vetted for building maintenance & accelerators operation by a subgroup of MAC for Tier 0 computing by an ad hoc expert committee for research by ECE Evaluation of costs: Infrastructure maintenance Accelerators operation Tier 0 computing Research all endorsed KHuK, Bad Honnef, 6/12/13
  19. FAIR Research Division @ Runtime 2020 FAIR Management’s Proposal 210 Researchers 32 Engineers & Technicians KHuK, Bad Honnef, 6/12/13
  20. Comparison with Other Labs KHuK, Bad Honnef, 6/12/13
  21. Thank you very much