This update provides a view of the progress made from April 22nd, 2019 to May 20th, 2019 at Minuteman Vocational Technical Regional High School. It includes updates on flooring, equipment installation, markerboards, plumbing fixtures, greenhouse framing, ceramic tile, ceiling tile, locker installation, and more.
E N D
Minuteman Vocational Technical Regional High School Progress April 22nd 2019 – May 20th 2019
May 20thView of Area A+B – Upper Level Corridor Flooring Substantially Complete May 20thView of Area A+B – Lower Level Specialty equipment installed in Lab Spaces. Flooring activities in progress.
May 20thView of Area G – Upper Level Ceramic tile in bathrooms complete. Installation of plumbing fixtures complete. May 20thView of Area G – Upper Level Corridor Flooring Complete. Markerboards In Progress
May 20thView of Area G – Exterior Environmental Greenhouse framing in progress.
May 20thView of Area D – Upper Level Ceiling tile installation in progress Locker installation in progress Classroom Markerboards in progress May 20thView of Area D – Upper Level Ceramic wall tile and alcove areas in progress.
May 20thView of Area D – Gymnasium Overhead gym equipment complete. Acoustic Wall Panels complete. Wood Gym floor currently in progress.
May 20thView of Area D – Mechanical Room Final connections to cooling tower in progress. NGRID completed gas train & meter installation.
May 20thView of Area E – Upper Level Skylight soffit framing complete and taping is in progress. May 20thView of Area E – Bridge Level Flooring moisture mitigation complete, flooring installation to follow
May 20thView of Area E+F – Cafeteria Painting substantially complete. Ceiling grid installation in progress.
May 20thView of Area F – Lower Level Ceiling grid installation in progress. MEP devices installed in grid in progress. Epoxy floor preparation starts this week.
May 20thView of Area C – Theater Installation of tension grid system complete. Electrical rough-in for lights and devices in progress. May 20thView of Area C – Theater Installation of fire curtain in progress. Mechanical rigging hoists installed at fly loft elevation.
May 20thView of Area E – Courtyard Excavation and subgrade prep in progress. May 20thView of Area A+B – West Roadway Placing loam along drainage swale in progress. Perimeter of roadway prepped and fine grading in progress.
May 20thView of Faculty Parking Lot - South Utility drainage island complete. Sub and Fine grading in progress.
May 20thView of Faculty Parking Lot–North Underground utilities in progress in drainage islands. Sub and fine grading to commence this week.
May Construction Schedule Look Ahead: Area A+B & G • Complete Installation of Ceramic Wall Tile • Complete Flooring Installation • Continue Bathroom Partition Installation • Commence Punchlist Process Area D • Complete Installation of Ceiling Tiles • Complete Classroom Flooring Installation • Continue Marker/Tack Board Installation • Commence Corridor Flooring Installation Area E • Complete Prime painting on Lower Level • Complete Classroom/Office Flooring Installation on Upper and Bridge Levels • Complete Skylight finishes and paint. • Continue Millwork installation Area F • Complete Ceiling Grid Installation • Continue Installation of Ceramic Wall Tile • Commence Epoxy Floor Installation in both Kitchens • Commence Kitchen Hoods & Gas train installation Area C • Continue Sheetrocking activities • Continue Fire Curtain Rigging Installation • Continue Mechanical Hoist Rigging Installation • Commence Guidewall Installation Exterior/Sitework • Fine grading at Loop Road and Place asphalt binder at Loop Road and Faculty Parking lot Week of 5/20 • Commence installation of granite curbing in these areas. • Commence concrete sidewalk backfill and preparation.