BT Hardware Commissioning

BT Hardware Commissioning. BT Coordinated Systems System Tests TI 8 part downstream of TED87765 + injection system in point 8 Idem TI 2 / point 2 LHC Beam Dumping System in point 6 BT Equipment Injection kickers MKI in point 2 and 8 Tune/aperture kickers MKQA in point 4

jude
Download Presentation

BT Hardware Commissioning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BT Hardware Commissioning • BT Coordinated Systems System Tests • TI 8 part downstream of TED87765 + injection system in point 8Idem TI 2 / point 2 • LHC Beam Dumping System in point 6 • BT Equipment • Injection kickers MKI in point 2 and 8 • Tune/aperture kickers MKQA in point 4 • Beam dump kickers MKD and dilution kickers MKB in point 6 • Protection elements TCDS and TCDQ point 6 J.Uythoven, V.Mertens & B.Goddard HC review 13 Mai 2005

  2. Kickers MKI and MKQA • MKI point 8: • Installation: summer (generators, HV cables) autumn – winter (magnets) 2005 • Hardware Commissioning likely during spring / summer 2006 • Hardware Commissioning test procedures described in EDMS document 481639 • Need to be ready for Sector Test in November 2006 • MKI point 2 • Installation: t.b.defined • Hardware Commissioning in spring 2007 • Procedures defined & published, as for point 8 • MKQA point 4 • Installation: after MKI point 2 • Likely not synchronous with other HC activities in point 4 HC review 13 Mai 2005

  3. Beam Dumping System Point 6 • Kickers: • Installation extraction kickers MKD spring 2006 Installation dilution kickers MKB summer 2006 • Hardware Commissioning winter 2006 / 2007 • Procedures: EDMS document in preparation • Protection elements TCDS and TCDQ • Installation summer 2006 • Hardware Commissioning winter 2006 / 2007 • Procedures in same EDMS document as kickers, in preparation • Needs to be followed by reliability run of three months (of the complete beam dumping system !) • System level commissioning • In spring 2007 • In parallel with hardware commissioning in point 2 HC review 13 Mai 2005

  4. Main concerns • Detailed planning of equipment HC activities needed, especially to check for interferences (include in LHC planning!). • Detailed planning of system level tests (scheduling and responsibility) to be defined. • Critical path for TI 2 end and IR2 injection. • Beam dumping system reliability run to be included in LHC planning. HC review 13 Mai 2005