This update provides information on the progress of the Linac4 connection, including the rescheduling of hardware commissioning, installation of wire scanners and SEMGrids, and impacts on the schedule. It also highlights the completion of work on the Linac4 side and upcoming activities on the Linac2 and PS Switch Yard sides.
E N D
Linac4 ConnectionBroken Line 28/08/19 • Smoothing: 3 weeks allocated in SeptemberIMPACT on the schedule: rescheduling of the hardware commissioning • Installation of the wire scanners and SEMGrids next weekMINOR IMPACT on the schedule • Installation of the LBS.BVT10 to be confirmedMINOR IMPACT on the schedule • Smoothing ongoingRisk to IMPACT the schedule:Start of the ISTs delayed by one week
Linac4 Connection Linac4 side WORK almost COMPLETED follow-up Linac4 Hardware and Beam commissioning meeting • Completion of the Linac4 transfer line L4T • 3MeV beam tests completed • Smoothing of the overall Linac4 and transfer line will start started – to becompleted in September (weeks 37-38-39) Any additional activities must be announced and evaluated if compatible with the smoothing Today No activities on the beam line to keep references for smoothing No access No co-activities
Linac4 Connection Linac2 rack room side WORK COMPLETED follow-up Linac4 Hardware and Beam commissioning meeting • Reconfiguration of the racks room • EN-EL-ENP activities completed • Individual system tests of the power converters start ongoing Any additional activities must be announced and evaluated if compatible with the tests ACCESS FORBIDDEN on Tuesday 10th11th September Heavy handling on surface Today No activities No access
Linac4 Connection Linac2 tunnel side WORK almost COMPLETED follow-up Linac4 Hardware and Beam commissioning meeting • Reconfiguration of the Linac2 • Installation of the new demineralized water cooling pipes completed • Modification of the gallery access structure in progress Today No activities on the beam line to keep references for smoothing No access Smoothing No co-activities last access
Linac4 Connection PS Switch Yard side • Reconfiguration of the beam lines • (Re-)installation of the beam line BI and LBS in progress (work possible until 13th September, then 2020) • Re-installation of beam line equipment on LT completed, LTB completed, LBE in progress (remain wire scanners and SEMGridsnext week) • Alignment LT completed, LTB completed, LBE completed • Measurement completed and Smoothing start in progress • Vacuum connection, pumping and leak detection in progress • Local cabling in progress
Linac4 Connection PS Switch Yard side Smoothing No co-activities
Linac4 Connection PS Switch Yard side No access Smoothing No co-activities last access