1 / 20

Linac4 Status

Linac4 Status. M. Vretenar, 30.10.2008. Linac4 on the CERN site. Linac4 will be built at the place of the “Mount Citron”, a small hill made in the 50’s from the excavation materials of the PS. Position and orientation allow a future extension to the SPL. PS. PSB. PS2 - SPS.

Download Presentation

Linac4 Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Linac4 Status M. Vretenar, 30.10.2008

  2. Linac4 on the CERN site Linac4 will be built at the place of the “Mount Citron”, a small hill made in the 50’s from the excavation materials of the PS. Position and orientation allow a future extension to the SPL. PS PSB PS2 - SPS Transfer line to Linac2 Future SPL Linac4

  3. Linac4 Groundbreaking 16 October 2008, Linac4 Groundbreaking by CERN Director, R. Aymar

  4. Linac4 Groundbreaking

  5. Linac4 Groundbreaking – The team

  6. Linac4 – Milestones • June 2007: approval of the project by the CERN Council. • January 2008: official project start (budget available). • May 2007: Defined linac position and type of tunnel, start pre-integration. • November 2007 – April 2008: Preparation of CE tendering drawings. • May 2008: CE Tendering • September 2008: Contract attribution. • 22 October 2008: Start Civil Engineering works. • December 2010: Tunnel and Hall delivery. • December 2011: Move Front-End to the linac tunnel. • January 2012: Start installation of DTL, CCDTL, PIMS. • February 2012: Front-end re-commissioning. • May-October 2012: DTL, CCDTL, PIMS commissioning. • November 2012: Transfer line commissioning, start PS Booster modifications. • March 2013: Start of PS Booster commissioning with Linac4 beam. • June 15th, 2013: Start physics run with Linac4 beam.

  7. Linac4 Parameters H− particles + higher injection energy (160/50 MeV, factor 2 in bg2)  same tune shift in PSB with twice the intensity. Ion species H− Output Energy 160 MeV Bunch Frequency 352.2 MHz Max. Rep. Rate 2 Hz Max. Beam Pulse Length 1.2 ms Max. Beam Duty Cycle 0.24 % Chopper Beam-on Factor 65 % Chopping scheme: 222 transmitted /133 empty buckets Source current 80 mA RFQ output current 70 mA Linac pulse current 40 mA N. particles per pulse 1.0 × 1014 Transverse emittance 0.4 p mm mrad Max. rep. rate for accelerating structures 50 Hz Re-use 352 MHz LEP RF components: klystrons, waveguides, circulators. Chopping at low energy to reduce beam loss at PSB. • Structures and klystrons dimensioned for 50 Hz • Power supplies and electronics dimensioned for 2 Hz, 1.2 ms pulse.

  8. Linac4 Layout 45keV 3MeV 3MeV 50MeV 94MeV 160MeV H- RFQ CHOPPER DTL CCDTL PIMS Drift Tube Linac 352 MHz 18.7 m 3 tanks 3 klystrons 4 MW 111 PMQs Cell-Coupled Drift Tube Linac 352 MHz 25 m 21 tanks 7 klystrons 6.5 MW 21 EMQuads Pi-Mode Structure 352 MHz 22 m 12 tanks 8 klystrons ~12 MW 12 EMQuads RF volume source Radio Frequency Quadrupole (IPHI) 352 MHz 6 m 1 Klystron 1 MW Chopper 352 MHz 3.6 m 11 EMquad 3 cavities Total Linac4: 80 m, 18 klystrons Beam Duty cycle: 0.24% phase 1 (LP-SPL) <6% phase 2 (HP-SPL) 4 different structures, (RFQ, DTL, CCDTL, PIMS) Ion current: 40 mA (avg. in pulse), 65 mA (bunch)

  9. The 3 MeV Test Stand RFQ source chopper line • In construction in the South Hall extension. • - H- source (2008) • LEBT (2008-09) • RFQ (February 2010) • Chopper line (2008) • Diagnostics line (2010) • Infrastructure (1 LEP Klystron, pulsed modulator, etc.) - ready • In the front end are concentrated some of the most challenging technologies in linacs, and this is where the beam quality is generated. Early understanding and optimisation of front-end is fundamental for a linac project. diagnostics line klystron modulator

  10. The RFQ • Original idea: • Use the RFQ being built in France for the IPHI project, after the tests at Saclay. • However, • This RFQ is now late by >2 years. • Problems (microleaks) on 1st segment. • The design parameters (95 kV injection energy, length 6 m) are not optimum for Linac4. • Conclusion: • Decision (summer 07) to build a new CERN RFQ optimised for Linac4: • 45 kV injection, 3 m length. • CERN+CEA beam dynamics and RF design, • CERN mechanical design, based on INFN and CEA designs (TRASCO and IPHI). • c. Construction and brazing in the CERN Workshops.

  11. Linac4 accelerating structures Linac4 accelerates H- ions up to 160 MeV energy: • in about 80 m length • using 4 different accelerating structures, all at 352 MHz • the Radio-Frequency power is produced by 19 klystrons • focusing of the beam is provided by 111 Permanent Magnet Quadrupoles and 33 Electromagnetic Quadrupoles PIMS A 70 m long transfer line connects to the existing line Linac2 - PS Booster

  12. Linac4 accelerating structures DTL CCDTL PIMS 7-cell cavities in p-mode. With respect to the SCL, the PIMS : • has 5 times less cells (less machining time and cost). • needs about the same quantity of copper. • allows a simpler tuning (7 cells instead of >100, dummy tuners). • allows standardisation of the Linac4 frequency to 352 MHz. • has only about 12% less shunt impedance. Modules of 3 SDTL-type cavities with 2 drift tubes, coupled by 2 coupling cells. • Easy access and alignment of electromagnetic quadrupoles. • Relaxed tolerances on drift tube alignment. Conventional DTL structure with: • PMQs in vacuum inside drift tube. • no drift tube adjustment after installation.

  13. Accelerating structures: gradients, peak fields, margins on RF power Optimum gradient in the different structures determined by cost considerations. For calculations, structure cost 180-250 kCHF/m, RF cost 450-650 kCHF/W Maximum surface field limited to 1.8 Kilpatrick (considered as safe enough for a pulsed machine) Maximum cavity power (copper, beam) 1 MW for klystrons (LEP) giving 1.2-1.3 MW (~20% margin for regulation and losses in waveguides) 20% margin from theoretical Q-value for additional losses in cavities

  14. The Linac4 RF system Linac4 will reuse the stock of high-power klystrons coming from the old LEP accelerator: Initial configuration: 13 klystrons 1.3 MW, 6 klystrons 2.5 MW, 3 modulators 1.3 MW, 11 modulators 2.5 MW Final configuration (at the end of the stock of LEP klystrons): 3 klystrons 1.3 MW, 11 klystrons 2.5 MW, 3 modulators 1.3 MW, 11 modulators 2.5 MW

  15. Linac4 civil engineering Equipment building ground level Linac4 tunnel Linac4-Linac2 transfer line Low-energy injector Access building Pre-integration May – October 2007 Tendering drawings November 2007 – April 2008 Tendering May 2008, Contract to FC September 2008.

  16. Linac4 Work Breakdown Structure Total of 30 Workpackages

  17. Linac4 Master Plan • End CE works: December 2010 • Installation: 2011 • Linac commissioning: 2012 • Modifications PSB: shut-down 2012/13 (7.5 months) • Beam from PSB: 15.6.2013 White Paper

  18. Installation and commissioning

  19. Linac4 Budget Does not include: chopper line (built in HIPPI) 13 klystrons + waveguides from LEP Budget is covered by White Paper funding (55 MCHF) CERN budget for 2011-12 (38 MCHF)

  20. Linac4 Status (10/2008) • Civil Engineering works started 22.10.2008, delivery of building end 2010. • Safety File submitted to CERN Safety Commission, June 2008. Building approved. • Ion source almost completed, first beam tests end 2008. • 3 MeV Test Stand infrastructure completed. • Prototype modulator tested with LEP klystron in pulsed mode. • Prototypes of accelerating structures tested (CCDTL), in construction (DTL), in final design stage (PIMS). Material being ordered, construction of DTL and CCDTL will start in 2009. • Started preparation for large contracts (klystrons, modulators, magnets,…). • Detailed descriptions of Workpackages in preparation, project baseline will be frozen at end 2008. • Advanced negotiations for in-kind contributions with France, Russia (via the ISTC Organisation), Poland, Spain (via ESS-Bilbao), India, Pakistan, Saudi Arabia.

More Related