1 / 44

ALICE DCS project L.Jirden 22.11.01

ALICE DCS project L.Jirden 22.11.01. Goals and global requirements Project Organization System overview Status today Conclusion. DCS/ECS PROJECT GOALS. High level goal

kaethe
Download Presentation

ALICE DCS project L.Jirden 22.11.01

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ALICE DCS project L.Jirden 22.11.01 • Goals and global requirements • Project Organization • System overview • Status today • Conclusion ALICE DCS overview - L.Jirdén

  2. DCS/ECS PROJECT GOALS • High level goal “A working DCS ready for exploitation early 2006 allowing to control and operate the experiment during all modes of operation and according to defined requirements”. • Intermediate goals • System tests and test-beams • Pre-assembly • Installation • Commissioning ALICE DCS overview - L.Jirdén

  3. Main requirements • Integrate all activities necessary to operate the experiment • All detectors and infrastructure during runs and shutdowns • Easy to operate • 2 – 3 non-expert operators should be enough • Exclusive and concurrent operation • Allow for multiple operators • Individual operation of detectors and sub-systems • Access at all levels with unique access control • Automation • Standard procedures, learning system ALICE DCS overview - L.Jirdén

  4. Requirements cont. • Modular, scalable and flexible • Allow for changes and addition of devices, sub-systems or detectors • Reliable • Operational during runs and shutdowns • Redundancy for critical functions non-accessible during runs • Maintainable • Assume 15 years operation ALICE DCS overview - L.Jirdén

  5. Lennart Jirden • Andre Augustinus • Tarek Ben Ahmed 50% • Sorina Popescu (PJAS) • vacancy ALICE Controls Coord. team (ACC) DAQ Trigger Offline LHC M. Ext. Services ALICE DCS overview - L.Jirdén

  6. Lennart Jirden • Andre Augustinus • Tarek Ben Ahmed 50% • Sorina Popescu (PJAS) • vacancy ALICE Techn. Coord. Techn. Board ALICE Controls Coord. team (ACC) ALICE Controls Board (ACB) DAQ Trigger Offline LHC M. Primary Services Detectors ALICE DCS overview - L.Jirdén

  7. ATLAS Controls Coord. CMS Controls Coord. LHCb Controls Coord. IT-CO group EP Management Joint Controls Project (JCOP) • Lennart Jirden • Andre Augustinus • Tarek Ben Ahmed 50% • Sorina Popescu (PJAS) • vacancy ALICE Techn. Coord. Techn. Board ALICE Controls Coord. team (ACC) ALICE Controls Board (ACB) DAQ Trigger Offline LHC M. Primary Services Detectors ALICE DCS overview - L.Jirdén

  8. ECS/DCS Context Supervisory Function DCS ITS TPC MUON pixel strip drift T T p hv hv hv hv hv lv lv lv lv lv Detectors ALICE DCS overview - L.Jirdén

  9. ECS/DCS Context Primary Services Supervisory Function infrastr. magnet gas electricity cooling DCS safety access ITS TPC MUON pixel strip drift T T p hv hv hv hv hv lv lv lv lv lv Detectors ALICE DCS overview - L.Jirdén

  10. ECS/DCS Context Primary Services Associated Projects Supervisory Function infrastr. magnet LHC ECS gas Offline electricity Trigger cooling DCS safety DAQ access ITS TPC MUON pixel strip drift T T p hv hv hv hv hv lv lv lv lv lv Detectors ALICE DCS overview - L.Jirdén

  11. Sub systems ALICE DCS overview - L.Jirdén

  12. Detectors and sub-systems DCS . . . . . . . . . . . . 15 detectors ~ 20 sub-detectors ~ 6 sub-systems/sub-detector Several devices/sub-system ALICE DCS overview - L.Jirdén

  13. Controls slices DCS . . . . . . . . . . . . 15 detectors ~ 20 sub-detectors ~ 6 sub-systems/sub-detector >100 controls slices !! ALICE DCS overview - L.Jirdén

  14. Layer Structure Technologies Custom Commercial Configuration DB, Archives, FSM Storage Log files, etc. Supervisory layer WAN SCADA (PVSS) LAN DIM OPC Process Control layer LAN Communication Protocols Controller/ (LHC, Safety, ...) Other systems PLC VME VME/SLiC Field Bus PLC/UNICOS Node Node Field layer Field buses & Nodes Experimental equipment Sensors/devices Based on an original idea from LHCb Hardware architecture ALICE DCS overview - L.Jirdén

  15. Software frameworks Supervisory application SCADA Framework Supervision SCADA (PVSS) FSM, DB,web, Etc. Communication OPC, DIM ? Proc. Contr. Applic. Proc. Contr. Applic. Process control SliC UNICOS VME/PC (Linux) PLC (Step7,etc) ALICE DCS overview - L.Jirdén

  16. What is the PVSS framework ? • An integrated and coherent set of guidelines, tools and components • Standard monitoring and configuration panels • Standard script libraries, Finite State Machines, • Standard devices (CAEN HV, Wiener PS, etc) • At the disposal of sub-system developers • Each component is developed independently but in a coherent way to fit in the global system • For the two main types of components: Control Units (CU) Device Units (DU) ALICE DCS overview - L.Jirdén

  17. Software architecture ECS Commands … DCS DAQ … TRD TPC MUON EL Control Units (CU) TPC-FC TPC-RO TRIG TRACK Status and Alarms … FEE COOL LV HV Device Units (DU) FEC HEAT FEC CAEN5 ALICE DCS overview - L.Jirdén To devices

  18. Control Unit operator Parent dBase Command & status Command & status Logging Access handling Functionality (FSM) Configurat Alarm handling PVSS Command & status Command & status Child ALICE DCS overview - L.Jirdén Child

  19. Device Unit operator Parent dBase Command & status Command & status Logging Functionality (FSM) Alarm handling Configurat Device driver PVSS Setting & reading Device ALICE DCS overview - L.Jirdén

  20. Functionality (FSM) Ramping up States Transitions Standby- configure Con figured Standby On Configd- standby Configure On - ramping down Initialized Ramping down Off Off-Initializing Faults Failed Failed-off ALICE DCS overview - L.Jirdén

  21. Concurrent operation Operator A Operator B ECS Commands … DCS Control Units … TPC MUON Operator C TPC-FC TPC-RO TRIG TRACK Status and Alarms … FEE COOL LV HV Device Units FEC HEAT FEC CAEN5 ALICE DCS overview - L.Jirdén To devices

  22. Services overview • Infrastructure • Cooling & ventilation • Electricity • Detector Safety • Gas • Magnets • Access ALICE DCS overview - L.Jirdén

  23. Infrastructure DCS … TPC INFRAST detectors sub-det. TPC-RO TPC-FC … sub-systems … FEE COOL COOL RACKS AREA … devices FEC HEAT DEV1 DEV2 DEV3 ALICE DCS overview - L.Jirdén

  24. Cooling & Vent DIP DCS TC … TPC INFRAST JCOV detectors sub-det. TPC-RO TPC-FC ALICE ATLAS sub-systems … … FEE COOL COOL COOL VENT … devices FEC HEAT DEV1 DEV2 DEV3 ALICE DCS overview - L.Jirdén

  25. Electricity DIP DCS TC … TPC INFRAST EL detectors sub-det. TPC-RO TPC-FC ALICE ATLAS sub-systems … … FEE CRATE RACK CR1 12kV … devices FEC HEAT DEV1 DEV2 DEV3 ALICE DCS overview - L.Jirdén

  26. Detector Safety System hardwired information information via network action signal Sub-Detector Tracker Temp Temp,Humidity,Status, etc. Smoke,Gas Leak,etc. Technical Services DIP(LDIWG) CSS CSAM, CSE, etc. DCS Supervisory Layer (PVSS) Infrastructure DSS Sub-System Layer (PVSS) DSSFront-Ends Front-End Layer (PLC, …) Services (Power, Water, Gas) Experiment (Sub-Detector, Racks, Gas) ALICE DCS overview - L.Jirdén

  27. Gas DCS GAS DSS … … detectors TRD TPC TRD TPC … sub- detectors TPC-FC TPC-RO TPC-FC TPC-RO sub- systems … FEE COOL MIX PURIF PUMP devices FEC HEAT VALV FLOW MANO ALICE DCS overview - L.Jirdén

  28. Magnets DCS DIP … TRD TPC MAG … TPC-FC TPC-RO ALICE CMS … FEE COOL L3 DI-MUON COMP devices FEC HEAT DEV1 DEV2 DEV3 ALICE DCS overview - L.Jirdén

  29. DAQ, TRG, Offline, LHC machine ECS … DCS DAQ TRG Offline LHCm … TRD TPC … TPC-FC TPC-M FEE COOL … FEC HEAT FEC ALICE DCS overview - L.Jirdén

  30. DCS Planning 03 04 02 05 06 2001 WHAT and WHEN ? 1ST BEAM TODAY ALICE DCS overview - L.Jirdén

  31. DCS Planning 03 04 02 05 06 2001 BEAM OP. FINAL INST. COMMISS. PRE-INST. DESIGN PURCH. ALICE DCS overview - L.Jirdén

  32. DCS Planning 03 04 02 05 06 2001 BEAM OP. FINAL INST. COMMISS. PRE-INST. SOLUTION PROJECTED USER REQ. DOC. SUPERVISORY LAYER PROTOTYPE & TEST DESIGN PURCH. ALICE DCS overview - L.Jirdén

  33. Where are we today? • Focus on detector Process Control first • Presently defining requirements • Creating a “channel inventory database” • Producing an URD per detector; for each sub-system • Functionality • Devices • Parameters • Interlocks • Alarms • Logging • Operational aspects, state diagrams ALICE DCS overview - L.Jirdén

  34. Where are we today? • Prototyping common solutions • Three pilot detectors – 9 sub-systems: • Prototype TPC pilots planned for global TPC test in Sept 2002 • “Vertical slice” for HMPID in progress • TPC Readout • High Voltage • Low Voltage • Cooling • TPC Fieldcage • High Voltage • Low voltage (r-rod current) • Cooling (r-rod) • HMPID • High Voltage • Low Voltage • Fluid system ALICE DCS overview - L.Jirdén

  35. HMPID example ECS … DCS DAQ … TRD HMPID GAS EL LV LC HV GAS PHYS … EUTRON RADIAT PUMP CAEN5 ALICE DCS overview - L.Jirdén To devices

  36. HMPID example ECS … DCS DAQ … TRD HMPID GAS EL LV LC HV GAS PHYS EUTRON RADIAT PUMP … CAEN5 ALICE DCS overview - L.Jirdén To devices

  37. HMPID main panel ALICE DCS overview - L.Jirdén

  38. HMPID example ECS … DCS DAQ … TRD HMPID GAS EL LV LC HV GAS PHYS EUTRON RADIAT PUMP … CAEN5 ALICE DCS overview - L.Jirdén To devices

  39. Liquid circulation ALICE DCS overview - L.Jirdén

  40. FSM representation ALICE DCS overview - L.Jirdén

  41. Conclusion • ALICE DCS project re-launched since 6 months • Outline of DCS project approved and contacts with most detector groups established • Implementation strategy defined and work-plan in preparation • Controls Coordination team established now 3.5 people. • Pilot prototyping of common solutions just starting ALICE DCS overview - L.Jirdén

  42. TPC Cooling test (may 2002) FEC FEC FEC FEC FEC FEC FEC FEC FEC FEC FEC FEC FEC May 2002 Wago module ADC 0-10V PT1000 sensors Wago mPLC 0.1 0C stability PID Regulation Heater Flow meter Ethernet/TCP Fieldbus PC-OPC server PC-PVSS ALICE DCS overview - L.Jirdén

  43. Implementation strategy • A. Process control for the detectors • Identify common requirements • Design “ALICE common solutions” • Pilot applications - test cases • Collaboration ACC – detector groups • Aim to cover all main functions – minimize number of special cases • B. Operations and supervisory functions • Link detector process control to supervisory layer • Implement vertical slice & use PVSS framework tools • Pilot applications – test cases • Collaboration ACC – detector group – JCOP ALICE DCS overview - L.Jirdén

  44. Implementation strategy • C. Services • Determine required functions and responsibilities • Pilot applications – test cases • Collaboration ACC – detector groups – CERN services • D. Links to ALICE DAQ, TRG, offline • Initiate common projects • Pilot applications – test cases • Collaboration ACC – DAQ, TRG, offline – detector group • E. Links to LHC • Experiment common project (JCOP) ALICE DCS overview - L.Jirdén

More Related