Update on Power SuppliesDCS Workshop in Bologna 19 June 06 L.Jirden • LV • Concerns • Orders & deliveries • Maintenance • HV • Overview TB 16.3.06 L.Jirden
LVPS overview Wiener PL500/F12 TPC TRD PHOS CPV MU TRK MU TRG Arem Pro SDD non-CERN contract Caen EASY SPD FMD PMD ACORDE SSD non-CERN contract HMPID non-CERN contract Caen SASY TOF non-CERN contract Caen SY1527 T0 non-CERN contract? V0 TB 16.3.06 L.Jirden
USERS: No PS TPC 20 TRD 90PHOS 6CPV 3 MU-TRK 30MU-TRG 6TOTAL ~ 155 Wiener PL512 MAIN CONCERNS:- Long delivery delay CR4 UX Ethernet water cooled 230 VAC 1ph 3U 2-8V:10A25A 50A100A 5-15V:10A20A TB 16.3.06 L.Jirden
Order and delivery - Wiener • Test Samples • TPC, MTG, MTK, TRD • delivered external interlock cabling added this week (w25) • Bulk order • All ordered • Delivery schedule fixed • PHOS: mid June • MTK: end June and end September • TPC: September & November • TRD: end June - December • Delivery to CERN ESS group • Unpacking, entry into support dBase • Reception tests with semi-automatic tester • Patch panels • Being ordered – to be mounted and cabled by CERN/ESS • Temporary panels made up by André • Rack mounting prototype being prepared in demonstrator rack Bldg 4 • Installation at P2 starting in July • Bins, power units, water, cables • DCS TB 16.3.06 L.Jirden
USERS: No cratesSPD 6FMD 1PMD 6ACORDE 1HMPID 3SSD 18TOF 72TOTAL ~106 Ethernet 1527LC 4U A1676 FILTER 3U 380 VAC 3ph A3486 3U 48 VDC 6U Caen EASY CR4 UX MAIN CONCERNS:- Filter sensitivity to B-field- long delivery delays 5-15V:20A 2-8V:9A25A50A100A TB 16.3.06 L.Jirden
Order and delivery - Caen • Test samples • SPD, HMPID, TOF: have some EASY systems (no filter units) for test • Bulk order • SPD,FMD,PMD,ACORDE: requested via ESS group; orders being issued now • HMPID,TOF: ordered directly to Caen • SSD: special module - ordered? • T0/V0 (SY1527 system): ordered? • Technical problems • Power factor, efficiency, connectors: being solved by Caen • Filter unit: B-field sensitivity being tested this week (w25) • Delivery • CERN contract: being negotiated but earliest October 06 • Other contracts (HMPID, TOF, SSD): ? • T0/V0: ? • Reception, unpacking, test: done by ESS group (if no objections) • Installation and commissioning: • Earliest November 06: are replacement devices required for FMD, ACORDE? TB 16.3.06 L.Jirden
Order & delivery –Arem Pro • SDD is the only user • Test samples ok: ? • Technical problems: ? • Delivery dates: ? • Installation and commissioning: ? TB 16.3.06 L.Jirden
Maintenance • Caen & Wiener • On-site maintenance and repair foreseen • avoids possible problems due to INB • Organized and handled by CERN ESS group • Arem Pro: ? TB 16.3.06 L.Jirden
HVPS • No common purchasing done • Each detector to take care of their own orders • Order via Institute or via CERN • Via CERN: contact D.Gregorio, CERN Purchasing • Time to order now • Common effort and support for control part • OPC server, Framework components, etc TB 16.3.06 L.Jirden
CAEN HVPS overview ISEG TB 16.3.06 L.Jirden