Spectrometer Solenoid Design and Test Results Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009
MICE Cooling Channel Layout Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Topics • Magnet 1 design features • Magnet 1 testing results • Modifications for Magnet 2 • Magnet 2 test results • Photos for discussion Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Magnet 1 Original Design Cold head 2nd stage Cold head 1st stage Vapor return lines LHe lines Cold mass Radiation shield Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Temperature Sensor Locations TPR: platinum resistor TRX: Cernox HTR: heater TSD: silicon diode VTM: voltage tap Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Magnet 1 Testing Results • Magnet cold mass was successfully cooled down to <5K using a combination of LN and LHe • Cool down of the shield was very slow as there was no direct connection to the LN (i.e. shield cooling by radiation and conduction thru cold mass suppts only) • LHe was boiling off from cold mass at a high rate • Helium was not being condensed at all by the coolers • Since the magnet was cold, an attempt was made to train the coils Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Magnet 1 Testing Results (cont’d) • The training reached 196 A in all coils (270 A needed to reach 4 T in the central coil) • Magnet training was discontinued when the available cryogens ran out and so modifications could begin • Based on measurements and observations, the coolers were not maintaining the LHe level, and the shield temperature was ~120 K rather than the specified 80 K • These two issues were due to the thermal siphon line being plugged by frozen N2 and an inadequate thermal connection between the cooler 1st stages and the shield Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Magnet 1 Testing Results (cont’d) • The blocked helium lines was mainly a procedural and partially a design issue • Also, the pressure rise observed within the cold mass during quench was too high • It was determined that the venting of the cold mass during quench was not sufficient due to crowding of the single vent line with instrumentation wires • Several mechanical issues also arose: magnet alignment in vacuum vessel, support stand height, iron shield support pads, support stand offset Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Magnet Design Modifications • Based on the results of the Magnet 1 testing, several design modifications were proposed • Work proceeded to complete the Magnet 2 assembly with design changes while starting Magnet 1 disassembly • A new cold mass cooling scheme was devised as well as an improved cooldown procedure • The 1st stage radiation shield connection was modified an an attempt to increase the thermal conduction • An additional vent line was added to the cold mass • An LN reservoir was added for direct cooldown of shield Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Magnet Cooling Configurations Cold head Condenser Larger diameter Cold mass shell Direct connection LHe line Coils No trap LHe Trap Original Design Design Option A Design Option B (not adopted) (Magnet 1) (Magnet 2) Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Cryostat and Cooling System Mods Cold head 1st stage Direct cryostat connection option 1100 Al radiation shield connections Additional vent line Radiation shield Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Modified Recondensing System Liquid/vapor He accumulator and cryocooler sleeves Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Liquid Nitrogen Reservoir • Reservoir provides direct LN cooldown of shield • May improve thermal connection between 1st stage of cryos and shield • Frozen mass of nitrogen protects leads in event of power failure (if LN is left in reservoir and temp. is low enough) Vent/fill lines (3) 1st stage cooler connection LN reservoir Thermal plate connection Radiation shield Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Magnet 2 Testing Results • After completing the described modifications earlier this year, an attempt was made to cool Magnet 2 with cryogens • An ice blockage developed within the cold mass fill line • The fill line geometry (90° bends) prevented clearing of the blockage, and the vendor moved the stinger to a vent line • Continuing the fill process led to a leak in a Conflat flange in the 2nd vent line (the one not being used for filling), venting the vacuum space to helium and aborting the cooldown • The Magnet 1 fill line routing has been changed to avoid sharp bends and thus improve the ability to clear a blockage Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Magnet 2 Testing Results (cont’d) • After warming up the magnet, the Conflat flanges were replaced with welded joints • Since the fill line blockage was likely a procedural issue, a safer and more robust technique for cooldown was devised (Bross/FNAL) and has worked well • The subsequent cooldown was successfully completed in only ~3 days w/o incident • However, the shield temperature fell slowly to only about ~115 K at the ends of the cylinder, resulting in added heat flow into the cold mass via the cold mass supports Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Magnet 2 Measured Temperatures 80K (no current) 90-95K (182 to 238 A) Not working 74K 65K 102K min No other shield sensors here Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Magnet 2 Testing Results (cont’d) • The improved(?) shield thermal connections and the LN reservoir did not solve the previous shield problems • The coolers are expected to maintain the LHe level after filling; ~1% of the LHe was being lost overnight (unpowered) • At this point, training began and appeared to be going well • The magnet underwent five training quenches at currents ranging from 182 to 238 A • At 238 A (w/all coils in series), one of the HTS leads burned out due to a higher than allowable temp. at the upper end Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Magnet 2 Testing Results (cont’d) • The upper lead temperature without current was ~80 K, increasing to >90 K with current, eventually resulting in failure of the lead farthest from the coolers • The lead problem was a surprise, as it was not noticed in the earlier Magnet 1 tests; the feedthroughs and all the leads are the same ones used before in Magnet 1 • We are currently thermally testing the feedthroughs and leads in an off line test to see what can be learned Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Testing Results Discussion • Changing flexible connection does not appear to have had a major impact on shield temperatures • New Al straps are thicker than the original Cu, but the Cu conductivity was better and the original straps were shorter • Our vendor, Bert Wang, has stated that he believes the connection to the shield is inadequate • There have been no indications of vacuum problems other than the seal failure that occurred in the vent line • No local icing has been observed on the vacuum vessel • Temperature measurements using a thermal laser probe have not revealed any irregularities Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Photos for Discussion Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Upper Leads and HTS Leads Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Upper Leads and Thermal Intercepts Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Upper Leads and 300K Feedthrough Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Upper HTS Leads Thermal Intercept Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
SC leads at cold mass feedthrus Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Coil Taps & Intercepts for Lower HTS Leads Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Coil Taps & Intercepts for Lower HTS Leads Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Magnet 2 HTS Leads (right lead burned out) Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Radiation Shield Thermal Connection 6061 Al cylinder ~6 mm thick Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Upper Thermal Shield Connection 1st stage Cu plate Cu/Al transitions (10 each) 6061 Al cylinder ~6 mm thick Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Magnet 1 Shield Flexible Connection OFHC copper straps Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Magnet 2 Shield Thermal Connection 1100 series aluminum connection to thermal shield (previously thin copper) Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Magnet 2 Shield with Flexible Connections Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Plates Welded to Shield for LN Reservoir Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
MLI Wrapped Cold Mass and Shield Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Partially Assembled Magnet Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Close Up of Cold Mass End Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
MLI on Shield & Vacuum Vessel Inner Bores Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
MLI Wrapped Cooler Sleeves and Leads Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Cold Mass Connections (Magnet 1) Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Cold Mass Support during Fit Up Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Cold Mass Support Connection to Shield Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Thermal Shield Support Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
Temperature Sensor on Cold Mass Bore Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009
LHeCooldown of Magnet Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009