100 likes | 254 Views
Spectrometer Solenoid Update. MICE VC 150 August 23, 2012. Steve Virostek - LBNL. Topics. Summary of initial magnet training Burned out HTS lead Second series of magnet training Schedule. Initial Magnet Training. First magnet cooldown completed on 5/25/12
E N D
Spectrometer Solenoid Update MICE VC 150 August 23, 2012 Steve Virostek - LBNL
Topics • Summary of initial magnet training • Burned out HTS lead • Second series of magnet training • Schedule
Initial Magnet Training • First magnet cooldown completed on 5/25/12 • Excess cooling capacity found to be >3 W • Start of training delayed by helium shortage • LHe issue solved with help from Fermilab • Seven training runs were carried out between 6/13/12 and 7/3/12 • Quench currents ranged from 185 A in all coils to 185 A in M1 and 245 A in M2 and E1/C/E2 • Frequency of runs largely dictated by LHe supply
Magnet Training (cont’d) • Numerous issues have arisen during the training that delayed progress but, for the most part, have been solved • These include: LHe supply, level gauges wiring problem, cold mass leaks to atmosphere, inadvertent quench triggered by QP system, circuit breaker trips, power supply stability • The most severe problem was a burnout of one of the six high-current HTS leads
HTS Lead Burnout • During the 7/3/12 training run, it was discovered that the ‘E’ HTS lead connected to one of the end coils had burned out • Subsequent review of the test data revealed that the lead had exhibited a constant resistance of ~100mW during all of the recent training runs • The voltage across the lead had never reached a level sufficient to trip the quench system until it spiked above the 100 mV threshold at 245 A • The quenched lead burned out before the system could sufficiently reduce the magnet current
HTS Lead Burnout Top: recently failed lead; middle: previously failed lead; bottom: new lead
HTS Lead Resistances Failed Lead 10x better, but worrisome New Lead In the noise HTS lead resistances measured over numerous training cycles
2nd Series of Training Runs • The magnet was warmed up in order to replace the failed lead thru an access port • Pumpout of the insulating vacuum and cooldown completed 8/9/12 • Four training quenches carried out so far: • M1=110 A, M2=134A, E1/C/E2=135A • M1=132 A, M2=163A, E1/C/E2=161A • M1=141 A, M2=168A, E1/C/E2=169A • M1=144 A, M2=174A, E1/C/E2=174A • Another training run to be carried out today
2nd Series of Training Runs • The reason for the lower current quenches is not known • Our analysis of the data suggests that these are normal training quenches that are similar in nature to the previous series • The fast DAQ/QP system appears to be functioning normally, and the power supplies are stable (in manual mode)
Schedule • The schedule is a bit uncertain due to the unpredictability of the training • Once the training and warmup are complete, the support feet need to be welded on and the magnet prepared for shipping • LBNL on site technical manpower has been limited in recent weeks due to budget issues • Progress on the second unit has been somewhat slowed as well