Advanced Metering Interim Settlement Solution Project Update

This project update provides an overview of the delivery of the Advanced Metering Interim Settlement Solution, including new data loading process, settlement of distributed generation, and changes to ERCOT's IT infrastructure.

kimsimpson
Download Presentation

Advanced Metering Interim Settlement Solution Project Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PR80027_01 Advanced MeteringInterim Settlement SolutionProject UpdateTDTWGJune 3, 2009 Heather Day, Project Manager

  2. PR80027_01 Project Update - Overview Delivery of PR80027_01 Advanced Metering – Interim Settlement Solution includes: • The creation of a new usage data loading process for ERCOT to receive15-minute interval data from advanced meters; • Ability for Market to receive interval data from ERCOT using dynamic extracts (web services); • Ability to settle distributed generation received from advanced meters; and, • Changes to ERCOT's IT infrastructure and storage in order to accommodate the significant increase in 15-minute data used in settlements.

  3. PR80027 Project Update – Progress

  4. PR80027 Project Update – Key Project Assumptions TDSPs will send 1 and only 1 LSE file per zip file. Advanced Metering LSE interval data files will contain a maximum of 50k transactions. A transaction is comprised of a single day of interval data reads – 96 reads (92 or 100 if changing to or from DST). This project will not change how Non-Opt In Entities (NOIEs) submit interval data to ERCOT. This project will not change how TDSPs/MREs submit interval data for BUSIDRRQ ESIIDs. Provisioned advanced meters will be assigned a weather-sensitive IDR load profile. All usage data received is based on the central time zone.

  5. PR80027_01 Project Risks Known risks in executing the project: • Possible schedule delays should key contract or ERCOT resources be pulled from the project. • Mitigation: All required contractors identified and engaged. Resource efforts are continually monitored and any issues are addressed immediately with the resource manager. • Possible schedule delays if adequate storage, power and space is not available by go-live to support increased data volumes. • Mitigation: Working closely and continually with infrastructure team to ensure necessary storage, power and space if available to support project throughout development, at go-live and on-going. • Possible schedule delays due to competing with Nodal integration testing for limited iTest environments • Mitigation: Detailed coordination steps are being identified and refined to ensure that all parties are aware of competing activities, etc.

  6. PR80027 Project Update – Market Testing • Scope of Market Testing: • TDSP submits Advanced Metering LSE interval data file submission and ERCOT returns a file-level acknowledgement • Target Dates for Market Testing: • October 19 – November 6, 2009 • Next Steps: • As the project progresses through development activities and the detailed ERCOT testing schedule is refined, coordination activities will be scheduled with the TDSPs. • Discussions with TDSPs targeted for July/August.

  7. Questions?