1 / 34

Status and Installation Plan for the Spectrometer Solenoid Magnets

Status and Installation Plan for the Spectrometer Solenoid Magnets. Steve Virostek Lawrence Berkeley National Lab. MICE CM17 @ CERN February 24, 2007. MICE Cooling Channel Layout. Spectrometer Solenoid 1. Spectrometer Solenoid 2. Spectrometer Solenoid Overview.

Download Presentation

Status and Installation Plan for the Spectrometer Solenoid Magnets

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status and Installation Plan for the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE CM17 @ CERN February 24, 2007

  2. MICE Cooling Channel Layout Spectrometer Solenoid 1 Spectrometer Solenoid 2 Steve Virostek - - - Lawrence Berkeley National Laboratory

  3. Spectrometer Solenoid Overview • Order for two spectrometer solenoid magnets was placed with Wang NMR by LBNL in June ‘06 • Design review was held by Wang on Sept 6, 2006 • Complete design package book provided to LBNL • Detailed magnet design is complete and fabrication is well under way • First magnet shipment expected by Sep 07 • Second magnet to follow ~6 weeks later Steve Virostek - - - Lawrence Berkeley National Laboratory

  4. Spectrometer Solenoid Fabrication Update • First machined coil former delivered to Wang • Preparation for coil winding is under way • First two cryocoolers to arrive at Wang on Feb 28th, two additional to follow two weeks later • Quench protection assemblies are near complete • Winding of fiberglass cold mass support bands will begin in early March • 50A HTC procured, 300A leads coming next week • Magnet instrumentation is on order Steve Virostek - - - Lawrence Berkeley National Laboratory

  5. Lead Neck Cooler Neck He Filler Neck Cold Mass Support PMT Iron Shield Space for Radiation Shield Support Stand Steve Virostek - - - Lawrence Berkeley National Laboratory

  6. 4.2 K Coolers Lead Neck He Gas Pipe Condenser Tank Cold Mass Cold Mass Support Liquid Pipe 4K End 60K Intercept 300K End Steve Virostek - - - Lawrence Berkeley National Laboratory

  7. Cold Mass with 50 Ton Support System 300 K Support End Cold Mass Assembly 60 K Support Intercept Support Band 4 K Support End Steve Virostek - - - Lawrence Berkeley National Laboratory

  8. Spectrometer Solenoid Cold Mass Passive Quench Protection Space Coil Cover End Coil 1 690 mm Match Coil 1 2544 mm End Coil 2 490 mm Center Coil Liquid Helium Space Match Coil 2 Coil Spacer Steve Virostek - - - Lawrence Berkeley National Laboratory

  9. Design Overview (coil construction) • Single piece 6061-T6 aluminum coil former • Each layer wet wound using Stycast 2850 FT • 2.5 mil thick fiberglass between winding layers • Passive quench protection will be provided by a system of diodes & resistors • Aluminum coil banding will provide hoop force support and ensure coils are tight after cooldown • Conductor joints are to be lapped by at least 24” to minimize the I2R losses Steve Virostek - - - Lawrence Berkeley National Laboratory

  10. First Completed Coil Winding Form Steve Virostek - - - Lawrence Berkeley National Laboratory

  11. First Completed Coil Winding Form Steve Virostek - - - Lawrence Berkeley National Laboratory

  12. First Completed Coil Winding Form Steve Virostek - - - Lawrence Berkeley National Laboratory

  13. Vacuum Leak Check of Coil Winding Form Steve Virostek - - - Lawrence Berkeley National Laboratory

  14. Vacuum Leak Check of Coil Winding Form Steve Virostek - - - Lawrence Berkeley National Laboratory

  15. Vacuum Leak Check of Coil Winding Form Steve Virostek - - - Lawrence Berkeley National Laboratory

  16. G-10 Material for Coil Side Insulation Steve Virostek - - - Lawrence Berkeley National Laboratory

  17. Coil Winding Apparatus Steve Virostek - - - Lawrence Berkeley National Laboratory

  18. Coil Winding Apparatus Steve Virostek - - - Lawrence Berkeley National Laboratory

  19. Quench Protection & Power Supply Hookup Steve Virostek - - - Lawrence Berkeley National Laboratory

  20. Quench Protection Diodes and Resistors Steve Virostek - - - Lawrence Berkeley National Laboratory

  21. Quench Protection Diodes and Resistors Steve Virostek - - - Lawrence Berkeley National Laboratory

  22. Quench Protection Diodes Steve Virostek - - - Lawrence Berkeley National Laboratory

  23. Quench Protection Resistors Steve Virostek - - - Lawrence Berkeley National Laboratory

  24. Quench Protection Assembly Parts Steve Virostek - - - Lawrence Berkeley National Laboratory

  25. 50 Amp High TC Leads Steve Virostek - - - Lawrence Berkeley National Laboratory

  26. Winding Form for Cold Mass Support Bands Steve Virostek - - - Lawrence Berkeley National Laboratory

  27. Example of a Cold Mass Support Band Steve Virostek - - - Lawrence Berkeley National Laboratory

  28. Example of a Quench Protection Assembly Steve Virostek - - - Lawrence Berkeley National Laboratory

  29. Example of a Cold Mass Support System Steve Virostek - - - Lawrence Berkeley National Laboratory

  30. Pulse Tube Cryocoolers • Two 1.5 W PT415’s will cool magnets to 45 K (1st stage) & 3.8 K (2nd stage) • ~0.05 T field @ cooler rotary valve motors (no iron shielding needed) • Up to three coolers per magnet can be installed and removed without breaking cryostat vacuum • Four units ordered by IIT – 1st two to arrive Feb 28th, 2nd two in ~2 weeks PT415 Pulse Tube Steve Virostek - - - Lawrence Berkeley National Laboratory

  31. Magnet Power Supplies • Three power supplies of +300 A at ±10 V for the center and two match coils (shared for 2 magnets) • Four power supplies of ±50 A (may need 2 @ 60 A) at ±5 V for the two end coils (2 per magnet) • Power supply specification is nearly complete • Resolve issue of whether quick discharge circuit is needed • Address computer interface question • Settle on quantities (testing, operation @ RAL, spares) • 3 month lead time – place order soon after CM17 Steve Virostek - - - Lawrence Berkeley National Laboratory

  32. Updated Schedule Summary Steve Virostek - - - Lawrence Berkeley National Laboratory

  33. Installation Plan and Issues • Integration discussions ongoing with RAL • Module connection to rail system resolved • Required lifting features being finalized • Requirements for transfer through door of MICE hall @ RAL established • Flange sealing options being discussed • Vacuum pumping requirements defined Steve Virostek - - - Lawrence Berkeley National Laboratory

  34. Summary • Detailed magnet design is complete • 1st coil former at Wang & ready for winding • 50 A HTC leads at vendor (300 A to follow) • Two cryocoolers to arrive on Feb 28 • P.S. spec is nearly complete – order ASAP • Expect 1st magnet complete by Sep 07 • Second magnet to follow ~6 weeks later Steve Virostek - - - Lawrence Berkeley National Laboratory

More Related