110 likes | 121 Views
Prototype Service Quarter Panel and Forward Disk Section update. ID Week February 2006. PQSP Status and Plan. Work at LBL is complete and it’s being packed up. Expect to ship from LBL this Friday (Feb. 17) to arrive at Bat. 154 in about one week
E N D
Prototype Service Quarter Panel and Forward Disk Section update ID Week February 2006
PQSP Status and Plan • Work at LBL is complete and it’s being packed up. • Expect to ship from LBL this Friday (Feb. 17) to arrive at Bat. 154 in about one week • LBL personnel( tech, student, senior citizen) arrive about Feb. 27 to set up Cirris tester and do reception testing of electrical connectivity • Loading of fibers and opto-boards and subsequent testing, checking interface with cooling parts is next critical step (and should happen in parallel) • Need validation of design/fabrication of PQSP optical items by end March to maintain schedule for production quarter service panels • Goal is to deliver first production SQP in April. HEX will be limiting factor unless something found in optical mounting. E. Anderssen LBNL
Vvdc at PP1 • First 4 harnesses made before pinout was finalized (affects 16 lemo power connectors) • Terminal Blocks for Vvdc Replaced • Vvdc and Vvdc Sense routed thru 1 of two Lemo connectors • Jumpers are designed and will be fabricated which remap these to ‘Production’ PP1 pinout • Should be delivered ~ April • QA Testing likely needs to be done with old pinout due to schedule constraints E. Anderssen LBNL
PSQP PP1 as completed • This will be the shipping configuration of the PSQP • For Acceptance Testing, the PP1B panels are welded to the base, but will be held at R450 in the test • This fixture may be used in system test, but will require some modifications for gas seal E. Anderssen LBNL
Optical Service loading configuration • All SQP’s held inverted to allow population of PP1 penetration with Ribbons • Previous slide shows backbone reinforcement required to flip panels • Opto-heat exchanger shown installed underneath backbone (on top in this picture) • ENV feedthru removed for this operation E. Anderssen LBNL
Environmental Sensors • Env connectors (4 lemo’s worth) wired in thru ISP slot • Internal locations all terminated with 2-pin connectors—blue pads in foreground of right pic • Do not have NTC’s or Humidity sensors at LBNL—will need to install all of them here • May need some E-tech (someone who can really solder) time from an institute to facilitate this E. Anderssen LBNL
Use of Spares • Spares in the production SQP’s are fully wired ‘PP0 Boards’ (serves up to 6/7 modules)—all connected at PP0 and PP1 electrically • Spares used in event of broken internal SQP components/connectors/pins etc • Only work if fully serviced with appropriate flavor of Opto-board, and if they are fully servicable externally • Discussion of what level of external infrastructure needs to be present to use Internal Spares might be an appropriate exercise for this group • Infrastructure is of course both physical services, but can also affect software/DB modularity as use of internal spares changes external mapping/modularity E. Anderssen LBNL
Disk Status • This is not my responsibility—so this represents only my limited understanding of the status • Defer to Gil for scheduled completion • Preparation for electrical QA testing underway in recently occupied clean room • As of yesterday—all disks populated with sectors, preparation of auxiliary tooling underway to mount U-tubes—first U-tube mounted, but need to align sector tubes to install remaining • Delivery of PEEK fasteners allowed mounting of all strain reliefs (tube and cable) to all disks • Should be mounting and inserting first disk in End frame this week—only a test as no capillaries are available • Believe we are on schedule for April delivery, but capillary is on CP (Gil?) E. Anderssen LBNL
Disk assembly on fixture E. Anderssen LBNL
U-Tube installed E. Anderssen LBNL
Cable and Tube strain Reliefs (SLA) E. Anderssen LBNL