1 / 18

E.Clément GANIL AGATA Days February 2013

AGATA Campaign at GANIL. Setup to be integrated AGATA@GANIL: Project Organization and Planning Status of the installation. E.Clément GANIL AGATA Days February 2013. AGATA 1 p at GANIL : Ancillary devices . Angles >10 deg for fission & MNT. At 0° as separator ( vaccum /gas-filled).

lamya
Download Presentation

E.Clément GANIL AGATA Days February 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AGATA Campaign at GANIL • Setup to be integrated • AGATA@GANIL: Project Organization and Planning • Status of the installation E.Clément GANIL AGATA DaysFebruary 2013

  2. AGATA 1p at GANIL : Ancillary devices Angles >10 deg for fission & MNT At 0° as separator (vaccum/gas-filled) In G1 coupled to VAMOS (+ EXOGAM2): SIBs, RIBs • Charged particle array for transfer reaction MUST2/TIARA : (d,p) etc … program with SIB and RIB • Charged particle array for prompt tagging : DIAMANT • Neutron detector (Nwall) • Charged particle array for Recoil Decay Tagging : MUSETT • Scintillator : BaF2 array, LaBr3 • Future detector : NEDA (n) , GASPARD ( ?), PARIS (LaBr3) E.Clément GANIL AGATA DaysFebruary 2013

  3. We have received 47 Letters of Intents • The equivalent of ~2006 UT are proposed • 16048 hours of beam on target (669 days) • 4 main setups • Vamosin magnetic spectrometer • Vamos in gas-filled • Nwall + Diamant • DSSSD • We need to organize sub-campaigns by setup and investigate the technical issues case by case : •  Working Group, leader to be identified during the workshop • Planning of upgrade of some ancillaries (gas-filled, NWALL, DIAMANT) • AGATA will increase in efficiency during the campaign • Not all experiments will benefit from the 1p E.Clément GANIL AGATA DaysFebruary 2013

  4. You might be invited to provide expensive isotopes for the accelerator (48Ca, 70Zn…) GANIL have some limitation for low beam energy 40,48Ca and 56Ni beams  issues to be discussed in the WG • GANIL cannot produce all of them : • Metallic 238U • 48Ca target is a challenge • Plunger Target  Joa’stalk • To be discussed within the Working Group E.Clément GANIL AGATA DaysFebruary 2013

  5. AGATA Configurations at GANIL EXOGAM, LaBr3, BaF2 … E. Farneaet al, Nuclear Instruments and Methods in Physics Research A 621 (2010) 331–343 SeeJohan’s talk E.Clément GANIL Scientific Council February 2013

  6. Organisation • Local organization done • Tasks distribution and their detailed description were distributed • GANIL project : • Set of spec delivered, detailed planning, resources evaluation, budget, development plan, PBS, WBS distributed • Security/safety : • Installation description for DIRC01 : •  1st draft released, risk analysis beginning of 2013 • The call for tender, to be launched by May 2013 after GANIL management review, are under preparation • Specific infrastructure to be delivered in December 2013 In 2012, ~4 FTE have worked on the project (20 persons involved at GANIL) For 2013-2014, ~80 m.month are evaluated E.Clément GANIL AGATA DaysFebruary 2013

  7. Schedule (assuming that material from GSI arrive on Jan-Feb 2014) Gas-filled installation expected in mid-2015 if funded in 2013 GANISOL beams available for physics beginning of 2016 No SPIRAL1 beam in 2014-2015 GANIL has requested the host of AGATA until end of 2016 E.Clément GANIL AGATA DaysFebruary 2013

  8. E.Clément GANIL AGATA DaysFebruary 2013

  9. Total investment cost ~380 k€ Detector lab infrastructure ~15 k€ Optical fibers links ~70k€ ~17k€ Processing room 019 Upgrade ~ 102k€ Cryogenic upgrade, connection ~25 k€ ~150 k€ E.Clément GANIL AGATA DaysFebruary 2013

  10. Budget : Total cost investment ~380k€ 237 k€ guaranteed by GANIL for 2013 to be completed in the 2014 request IPHC requested 90k€ from IN2P3-AP for the mechanic ANR (French Research Funding Agency) request for the gas-filled mode submitted by the Saclay and GANIL group (PI : Ch. Theisen & Ch. Schmitt) Loan of material from LNL & GSI (cooled cabinet, racks, water distribution, Optical link) under evaluation E.Clément GANIL AGATA DaysFebruary 2013

  11. Mechanic • Detectors support design done by STFC Daresbury in close collaboration with GANIL • GANIL designs the additional platform • GANIL takes in charge the integration work • Projection T1 -2013 • 9 months of construction estimated starting by T1-2013 • On-going collaboration with the IPHC workshop for the construction of the support • Workshop for the extended platform not yet defined I. Burrows (STFC) M. Ozille, P. Gangnant (GANIL) E.Clément GANIL AGATA DaysFebruary 2013

  12. Mechanic • First 2D projections have been released in January • On-going validation and fine cost estimate • Mechanical stress and rigidity calculations validated I. Burrows (STFC) M. Ozille (GANIL) G. Gaudiot(IPHC) E.Clément GANIL AGATA DaysFebruary 2013

  13. Mechanic M. Ozille (GANIL) E.Clément GANIL AGATA DaysFebruary 2013

  14. Target loader and beam line • GANIL is in charge of the beam section and target chamber design for most of the experiment • Specific configurations will be treated case by case • Target loader : • Detailed design on going by GANIL • Final decision will be taken after the workshop M. Ozille, P. Gangnant, G. Fremont (GANIL) E.Clément GANIL AGATA DaysFebruary 2013

  15. Integration Salle G1 300 opticalwires EXOGAM Elec. AGATA Elec. AGATA Cryogenic distribution DSS 27 kW UPS Water cooling 26° 8 bars L. Menager, J. Ropert, JL. Foucher (GANIL) E.Clément GANIL AGATA DaysFebruary 2013

  16. Integration L. Menager, M. Jean , N. Menard (GANIL) G1 cave The foreseen room required important investment (refurbishment, electricity, water cooling, air conditioning …) E.Clément GANIL AGATA DaysFebruary 2013

  17. Performance simulations : on-going (see Johan’s talk) • Electronic coupling: on-going (several meeting already done, transfer of knowledge in GSI during 2013) • Detector: starting (transfer of knowledge in GSI during 2013) • Data flow, DAQ: on-going (several meeting already done, no problem anticipated) • Mechanic design : on-going (final design review) • Optical link : on-going (Call for tender expected by April) • Data analysis : starting (first meeting on the first week of Dec.) • AutoFill-cryogenic : on-going (definition of the installation, call for tender in April) • Infrastructure : on-going (final design review on going) E.Clément GANIL AGATA DaysFebruary 2013

  18. Conclusion • Physics objectives will be presented at the next CS for evaluation (Campaign definition) • Sub-campaigns to be discussed and adjusted with upgrade planning • 2014-mid 2015 : AGATA-VAMOS+ “light” ancillary • 2015 : gas-filled, NWALL • 2016 : SPIRAL1 beams • The AGATA project at GANIL made progress in all different items with a particular attention on the mechanic and the integration • The transfer of knowledge on detectors and electronic will be organized in 2013 during off and on-beam period at GSI with GANIL technical staff. • Mechanical construction should start soon, delivery by end of 2013 • Call for tender are expected to be sent by May 2013 for infrastructure • Data Acquisition and Data analysis preparation will progress over 2013 • GANIL technical involvement is already significant • Budget guaranteed by GANIL for 2013 to be completed in the 2014 request E.Clément GANIL AGATA DaysFebruary 2013