Caltrans Bridge Construction Forum 2007. Structure Materials. Bill Corn Balfour Beatty Construction. Ken Bocchicchio California Department of Transportation. Structure Materials. Suppliers - What’s good or bad? Pre- qualification – Can there be more? QC/QA Paperwork -

laurie
Download Presentation

Caltrans Bridge Construction Forum 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Caltrans Bridge Construction Forum2007 Structure Materials Bill Corn Balfour Beatty Construction Ken Bocchicchio California Department of Transportation

  2. Structure Materials • Suppliers - What’s good or bad? • Pre- qualification – Can there be more? • QC/QA Paperwork - • Shortage of Materials and Suppliers

  3. What is good or bad as a supplier for Caltrans? • Is payment timely? • Are specifications consistent? • Would additional material indexing on long-duration projects reduce risk and cost? • Have new specifications impacted suppliers?

  4. Pre qualification • What procedures should be pre-qualified? • CIDH, Welding, Yellow Paint Removal? • What materials should be pre-qualified? • Concrete, asphalt, rock, cure? • What plants/shops should be pre-qualified? • Sign structure fabrication, pipe pile, light and signal poles?

  5. QC/QA Paperwork • Caltrans is moving toward the contractor being responsible for quality assurance. • Caltrans is moving away from method specifications and moving toward performance specifications.

  6. QC/QA Paperwork • Caltrans materials release process “Tagging” • Timing • Transfer Between Projects • Certificate of compliance to allow acceptance on site

  7. QC/QA Paperwork • Are requirements clear? • Is there too much paperwork required? • Is the ownership of the acceptance clear? • Which materials or operations do contractors want to provide QA?

  8. Shortage of materials and suppliers Why? • Because Caltrans is not the owner of choice? • Because the volume of work available nears the maximum capacity of suppliers? • Limitations on raw material?

  9. WHAT ARE THE ISSUES? • Late payment • Late material delivery • Incorrect QA/QC paperwork • Acceptance concerns

  10. SOLUTIONS ?