ISD2RYES NM. PCC Update 09/23/09 Planning Phase. Agenda. Budget Schedule Current Status Progress . Planning Phase Budget. * Commitments include requisitions and POs for Data Conversion specialists the contracts for which will extend into Implementation Phase II.
E N D
ISD2R\YES NM PCC Update 09/23/09 Planning Phase
Agenda • Budget • Schedule • Current Status • Progress
Planning Phase Budget * Commitments include requisitions and POs for Data Conversion specialists the contracts for which will extend into Implementation Phase II. * Also included in commitments are small contracts for two Solutions Architects, one with Application and one with System Architecture experience. The personnel RFP received no qualified candidates.
Planning Phase - Actual • Several minor changes were requested by FNS and CMS • Changes were made W/E 09/20/09 • ISD has the changes under review.
Planning Phase – Current Status • Green