An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ISD2 Replacement Project (ISD2R) PCC Update 07/23/10

  2. ISD2R Agenda • Objective • Background • Executive Review Including Health Care Reform • Sub-projects Reviews: • Budgets • Going Forward

  3. Objective Replace the Income Support Division (ISD), Integration Services Delivery (ISD2) System which manages benefits for over 700,000 clients who receive Food Stamps (SNAP), Energy Assistance , Medicaid, and Cash Assistance. Meet Requirements of Health Care Reform Act of 2010 Partner with the following Federal Agencies: Food and Nutrition Services (FNS) Centers for Medicare and Medicaid (CMS) Administration of Children and Families (ACF)

  4. Background The Replacement Project was submitted in Sept. 2006 and included three phases: Planning Web Access Replacement System By 2009 the Replacement Project focused on multiple Sub-Projects: Yes-NM Encounter Tracking Data Conversion Business Intelligence Imaging

  5. Executive Review In Jan-Apr 2010 an Executive Review took place. Key Questions on Project Scope: What is the core functionality? The Replacement System What do you need for “no wrong door” and access the core functionality? Web Access What do you need for key performance indicators? Reporting Executive Review Outcome: Planning for the Replacement System taking into Consideration Health Care Reform Action: Review off existing and potential replacement systems.

  6. Health Care Reform Systems Reviewed: Visited Michigan (Five member HSD team) Technology: A good fit Project Management Office (PMO) key to Michigan's success Demo from California on C-IV C-IV (Old): Technology is old; good graphical interface ASPS (New): Technology a good fit; good graphical interface Demo from Tennessee and Maine Acceptable fit for HSD and Health Care Reform Other Demonstrations/Conversations Deloitte, Microsoft, Northrop Grumman Determination: Send out an open RFP for an Integrator using a contracted Procurement Specialist.

  7. Sub-Projects The Scope of the Replacement Project is the Replacement System. What should be done with the Sub-Projects: Executive Review Outcome: Cancel or suspend all projects not associated with the Replacement System (ISD2R) Web Access (Public: Yes-NM, Staff: Encounter Tracking) Suspended Reporting (Data Conversion & Business Intelligence) Cancelled Imaging (Electronic Documents) Cancelled Funding sub-projects puts ISD2R at risk Resource contention implementing sub-projects puts ISD2R at risk

  8. Sub-Projects • Web Public Access: Yes-NM “Am I Eligible” • In production and M&O contract with vendor expires on 6/30/10 • Production and UAT environment must be maintained by DoIT and HSD-ITD staff • HSD must develop business processes to handle the inevitable increase in applications during a time of record high vacancies in field offices • Reporting (Replaced by “System Integrator”) • Encounter Tracking: Stopped at Proof-of-Concept • May be added to Integrator RFP • Business Intelligence: Supported with Internal Staff • May be added to Integrator RFP • Imaging: • May be added to Integrator RFP

  9. Funding & Budgets Analysis: Our State Laws funding the project have been interpreted for two parts of the project: Replacement System Yes-NM Our Federal Partners divided the Replacement Project into two phases: Planning Implementation Share represents the tracing of our laws: Z80727 - Replacement System Z80726 - Yes-NM

  10. Funding & Budgets Federal Partners Budget Approval Planning Budget Approvals 2006 $ 653,600 2009 $ 1,346,400 Total $ 2,000,000 Pre-Implementation Budget Approvals email dated Sept. 26, 2008 Imaging $ 2,500,000 Yes NM (limited) $ 1,163,190 Business Intelligence $ 618,000 Total $ 4,281,190

  11. Funding and Budgets Tie Fed Phases with Sub-Projects Fed Partners Planning and Implementation Phases Fed Partners 2006 APDU Phases 2009 Sub Projects State Laws with Share Z codes

  12. Fed Partners - Funding and Budgets Federal Budget Status For this calculation, each expense from the start of the project to the end of SFY10 was assigned to either Planning or Implementation.

  13. NM - Funding and Budgets Sub-Project Budget Status For this calculation, each expense from the start of the project to the end of SFY10 was assigned to a category. The categories consist of the sub-project or to the Replacement Project. The expenses for the Replacement Project are $784,238 Examples: contracts for PMP, APDU, IAPD,

  14. Funding & Budgets Expense balancing Federal Partners Expenses Planning $ ( 528,668) Implementation $ (2,579,965) Total $ (3,108,633) Sub-Project Expenses (Planning & Implementation) Replacement Project $ ( 784,238) Imaging $ ( 0) Reporting (DC & BI) $ ( 526,812) Web (ET & Yes) $ (1,797,583) Total $ (3,108,633)

  15. Going Forward Sub-Project Financial Tracking State Laws: Share = Z codes Fed Phases Planning and Implementation Phases Share = Operating Units Sub-Projects for Replacement System Share = Reporting Categories

  16. Planning Budget

  17. Going Forward • Actions: • Project Management Office (PMO) RFP • Responses due 7/23/10 • Deliver to the Federal Partners an updated Planning-APDU • Delivered on 7/7/10 • Procurement Specialist Contract • In HSD review • Re-submit to PCC a Change Cert at the Planning Phase • July 2010 • Issue open RFP for Replacement System including Integration

  18. Schedule

  19. Questions