150 likes | 168 Views
Construction and Performance Evaluation of Roller Compacted Concrete under Accelerated Pavement Testing TRB Paper No: 15-1944. Moinul Mahdi Zhong Wu, PhD., P.E. Tyson Rupnow, PhD., P.E. Jan 14, 2015. TRB Annual Meeting. Outline. Background Objectives Construction and Instrumentation
E N D
Construction and Performance Evaluation of Roller Compacted Concrete under Accelerated Pavement Testing TRB Paper No: 15-1944 Moinul Mahdi Zhong Wu, PhD., P.E. Tyson Rupnow, PhD., P.E. Jan 14, 2015 TRB Annual Meeting
Outline Background Objectives Construction and Instrumentation Accelerated Loading on RCC Pavement Sections Summary and Conclusion
Project Details • Six full-scale, RCC-surfaced pavement test sections were constructed at the PRF of LTRC • Each section: 71.7-ft long and 13-ft wide • Sections 1-3: Design alternative for those low-volume roads having significantly heavy truck traffic • Sections 4-6: Design alternative for high-volume roads using a treated subgrade layer
Project Details [cont.] • The final design gradation and corresponding RCC mix quantities used in this study were designed at the LTRC’s concrete research lab. • Cement contents for base layer were determined by DOTD TR 432 to achieve 7-day UCS of 150 or 300 psi. • 6% cement by volume was used for sections 1-3 (cement treated base) • 8% cement by volume was used for sections 4-6 (soil cement) • 4% cement by volume was used for treated subgrade
In Situ Testing Resultsduring the Construction of RCC Sections
In Situ Testing during the Construction • Field Testing Methods • FWD/LFWD • Surface roughness/walking profiler • RCC Surface Texture & Friction
FWD Backcalculated Layer Moduli 8”RCC+12CT 6”RCC+12CT 4”RCC+12CT Section 1 Section 2 Section 3 8”RCC+8.5SC 6”RCC+8.5SC 4”RCC+8.5SC Section 4 Section 5 Section 6
Surface Roughness, Friction & Texture • High Surface Roughness due to Paving Speed, Paver type, Manufactured sand and Coarser Aggregate Gradation • Similar to Superpave mixes on surface friction and macrotexture
Accelerated Pavement Testing - ATLaS30 ATLaS30 • Dual-tire load, 130 psi • Load: up to 30 kips • Speed: 3~6 mph • Bi-directional loading • Effective length: 42-ft • About 10,000 passes/day
Cracking and Pumping (8 in. RCC) • After 53,000 repetitions of 25-kip load, Section 4 developed both transverse and longitudinal cracking; • Joint pumping also observed under heavily raining weather, > 3 in. rainfall overnight
Results and Discussion (8 in. RCC) • The estimated ESALs based on AASHTO method ≈ 10.9 million • Based on Miner’s Cumulative fatigue damage law: • -the total damage > 100% when MR=600 psi • -the total damage ≈ 41% when MR=800 psi • Whether or not this should be considered as the test section failure is under further investigation Currently observing the Crack Propagation, Joint Faulting, IRI and any major visual distress to identify failure.
The Current Conditions of RCC Sections • Section 5 (6 in. RCC) • No distress was observed • Approximately 12.1 million ESALs • Further testing will be performed till failure. • Section 6 (4 in. RCC) • Several cracks, pumping and spalling was observed • Approximately 19.0 million ESALs • IRI values went up to 268.8 in/mile from 167.5 in/mile
The Current Conditions of RCC Sections CL 20’ 20’ Longitudinal Crack Length: 2’- 5” Transverse Crack Length: 2’ - 8” 8”RCC 15’ 15’ 15’ CL 15’ 6”RCC No Cracks 10’ 10’ 10’ 10’ 10’ CL 10’ Several Cracks are Observed 4”RCC
Summary and Conclusion • The failure criteria of RCC pavements under APT loading need further investigation; • As of now the tested RCC sections had performed better than expected; • Both RCC-Pave and PCC fatigue models did not seem to fit for the prediction of fatigue damage of this sections; • A new fatigue damage model is expected to be developed in this study for thin RCC-surfaced pavement.