1 / 33

Excavation Below Subgrade (EBS)

Excavation Below Subgrade (EBS). Topic G. EBS. QC/QV personnel do not determine/direct EBS operations. Engineer ultimately determines the need for EBS. EBS. Remove objectionable materials. Resulting excavation is then back filled with soil. Figure 3.1. Figure 3.1: Intercepting Embankment.

livia
Download Presentation

Excavation Below Subgrade (EBS)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Excavation Below Subgrade (EBS) Topic G Topic G

  2. EBS • QC/QV personnel do not determine/direct EBS operations. • Engineer ultimately determines the need for EBS. Topic G

  3. EBS • Remove objectionable materials. • Resulting excavation is then back filled with soil. • Figure 3.1 Topic G

  4. Figure 3.1: Intercepting Embankment Topic G

  5. Predicting EBS Areas • Groundwater levels = 3 feet or less. • Silty “B” horizon. • Topsoil depths exceed 12 inches. • Moisture levels above plastic limit. • Depositional characteristics (alluvial, lacustrine). Topic G

  6. Predicting EBS Areas • Roadway constructed prior to 1940. • Extensive filling. • Roadway is distressed. • Highly variable soil conditions exist. • Subgrade is within 2 ft. of original surface. Topic G

  7. Figure 3.2: Detail of EBS Topic G

  8. EBS • Remove uncertain soil. • Note the diagonal rutting= unstable silt. • In addition to excavation. Topic G

  9. Figure 3.3: EBS Topic G

  10. Topic I

  11. Rutting of Unstable Material • Transition from cut to fill are important. • Inspect before the subbase or base. • Rutting of unstable material shown. Topic G

  12. Figure 3.4: Rutting of Unstable Material Topic G

  13. EBS • Yielding water-bearing silt. • Rock truck-hauling material away. • Backhoe-Loading EBS material out. • Dozer-Pushing material to backhoe. Topic G

  14. Figure 3.5: EBS Topic G

  15. Backfilling EBS • EBS has to be measured. • Original section is template in the cross. • Final section • How much was excavated. Topic G

  16. Figure 3.6: Backfilling EBS Topic G

  17. EBS • Do not do EBS when rain is imminent. • Do not leave EBS excavation open over night. Topic G

  18. Topic I

  19. Figure 3.7: EBS Topic G

  20. Figure 3.8: Loading Unstable Material Topic G

  21. Backfilling EBS • Careful placement and compact backfill. • Use similar materials in area. Topic G

  22. Figure 3.9: Backfilling EBS Topic G

  23. Organic & Silty Soils • Have foundation support for equipment. Topic G

  24. Figure 3.10: Organic & Silty Soils Topic G

  25. Seepage in a Cut • Must correct area like this. • Ditches may work. • Riprapping • Underdrains • Vegetation will not grow. Topic G

  26. Figure 3.11: Seepage in a Cut Topic G

  27. Dust Abatement • Required to minimize dust. • Use water or dust control materials. Topic G

  28. Figure 3.12: Dust Abatement Topic G

  29. Stone Piles & Fences • Large rocks outside the shoulder point. Topic G

  30. Figure 3.13: Stone Piles & Fences Topic G

  31. Marsh Excavation • Picture 2: • Excavated marsh either cast out or loaded into marsh. • Used for deeper marshes. • Dragline works slower then backhoe. Topic G

  32. Figure 3.14: Marsh Excavation 1 Topic G

  33. Figure 3.15: Marsh Excavation 2 Topic G

More Related