380 likes | 546 Views
Experience Delivering Similar Systems. ABB Power Market Experience. Power Markets. North America. Europe. Asia. Australasia. South America. Africa. Pool Scheduling Systems Major ISO Systems. ABB Power Markets: North America. (EMS). ABB Power Markets: North America. California ISO:
E N D
Experience Delivering Similar Systems ABB Power Market Experience
Power Markets North America Europe Asia Australasia South America Africa Pool Scheduling Systems Major ISO Systems
ABB Power Markets: North America California ISO: Eight Years Operation Ontario IESO: Five Years Operation New York ISO: Five years Operation
Contract Signed March 1997 Systems Shipped September 1997 Systems Online March 1998 Combined ABB Market System and EMS System New real-time market went online October 1st 2004
PMS Contract Signed SA/SI/BBS Contract Signed PMS Factory Acceptance Test PMS Dry Runs Begin 6+ Month Development SA/SI/BBS Dry Runs Begin Extended Testing & Verification 7+ Month Development ISO Operational Apr Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar 1998 1997 1998
IESO Ontario (Canada) Power Market Design • New EMS • Look-ahead in R/T market • PASA ( • Direct message exchange with generators • New State Estimator • Multi-Interval Optimization (2004) • Enhanced real-time market online June 23rd 2004
Ontario (Canada) Power Market System First operational in May 2001 Significant changes implemented: • New EMS Replacement for old DAX system • Look-ahead in R/T market • PASA (predicted adequacy assessment) • Direct message exchange with generators • New State Estimator • Multi-Interval Optimization (2004) • Enhanced real-time market online June 23rd 2004
Partnership Master Agreement Signed August 1995 Systems Deliveries commenced in 1996 NYPP Converted to NY ISO in November 1999 Significant changes implemented: SCUC, look-ahead AGC, 5-min Real Time Market Major market redesign project started in 2003 New SMD Market in live operation since January 2005
NYSIO Market Design Very close to FERC SMD: • Signed August 1995 • Systems Deliveries • commenced in 1996 • NYPP Converted to NY ISO in November 1999 • Significant changes implemented: SCUC, look-ahead AGC, • 5-min Real Time Market • Major market redesign project started in 2003 • New SMD Market in live operation since January 2005
ABB in European Power Markets Stattnet: NordPool Market Endesa: OMEL (Spanish) Market RWEnet: RWEnet (German) Market TERNA: Italian Market National Grid: Original UK Market
UK GM Pool First site in world to use “SCUC”, developed by ABB in 1998
The KPX MOS Project • Contract signed January 2002 • Systems delivered August 2002 • Site testing finished October 2003 • Market Dry Run complete 2003 • Acceptance Certificate Issued 2003 • Live Market will commence this year 시스템구성: 계층구조
The KPX Market Design Korean Market Design: • Contract signed January 2002 • Systems delivered August 2002 • Site testing finished October 2003 • Market Dry Run complete 2003 • Acceptance Certificate Issued 2003 • Live Market will commence this year 시스템구성: 계층구조
KPX MOS Deliverables • Primary MOS • Backup MOS • Interface to 3rd Party EMS • PSSA /market training system • Development system • “Technology Transfer” to local partner KDN • Acceptance Certificate issued by KPX 2003 • Now under maintenance contract
Power Markets North America Europe Asia East China South America Africa Australia Pool Scheduling Systems Major ISO Systems
East China Grid Company Contract Signing March 2003
Contract Signed: March 2003 Integrated ABB EMS/MOS Phase 1 Market Opening Ceremony May 2004 Simulated Day-Ahead Market in Operation System Take Over Certificate March 2006 Total System Size 2006: 100,000 MW peak load East China Grid Company
Power Markets North America Europe Asia Philippines South America Africa Australia Pool Scheduling Systems Major ISO Systems
PHILIPPINES Wholesale Electricity Spot Market Contract Signing February 2004
Contract signed February 2004 Dev system delivered April 2004 FAT completed November 2004 SAT completed Manila 02/05 1-yr Market Readiness Trials Market in Live Operation since June 2006 First full-scale multi-commodity power market in Asia PHILIPPINES
Market Design: Hourly market with nodal pricing for generation and zonal pricing for consumption Week-Ahead, Day-Ahead, and Real-Time markets for energy and ancillary services Financial transmission rights Web-based infrastructure for bid/offer submission by market participants Prudential risk analysis Direct interface with EMS for exchange of market and grid data Advanced applications to perform dispatch and compute resulting MCPs Meter data aggregation, settlements and invoice generation Direct EFT interfaces with local banks, full accounting functionality for WESM PHILIPPINES
Systems Characteristics: Primary System Market Interface, Market Applications, Settlements, FTs, FTRs, Metering system (all ABB) Backup Site Interface to existing GE EMS Market simulation system Development system PHILIPPINES
PHILIPPINES Wholesale Electricity Spot Market Market Go-Live June 23rd 2006
Power Markets North America Europe Asia South America Africa Australia WesternAustralia Pool Scheduling Systems Major ISO Systems
Web-based infrastructure for bid/offer submission by market participants Prudential risk analysis Direct interface with the System Manager (EMS) for exchange of market and electric network data Advanced applications to perform the dispatch and compute the resulting MCPs Meter data aggregation and settlements and invoices creation Direct interfaces with local banks for EFT through AUSTRACLEAR Western Australia: Market Design
Western Australia Wholesale Electricity Market Contract Signing August 2005
Contract signed August 2005 Market Interface, Market Applications, Settlements FAT December 2005 Shipped in 5 months SATJan-March 2006 Market Trials Complete August 2006 Market Live Operation September 2006 Live 13 months AOC Western Australia Wholesale Electricity Market
Power Markets Ireland 2007 North America Europe Asia South America Africa Australia Pool Scheduling Systems Major ISO Systems
Ireland Single Electricity Market Contract Signing April 2006
Single Electricity Market for whole Island – two countries, two currencies Dual, interconnected computer systems in Dublin and Belfast to support internet power trading, financial settlements, energy dispatch and grid security Will be Etc Ireland SEM Market Design
Contract award to ABB April 2006 Prime Contract for all hardware and software infrastructure Systems development in Santa Clara May – November 2006 FAT in Santa Clara December 2006 Systems will ship to Dublin and Belfast in February 2006 Five month site testing and market trials Market will open July 2007 Will be the most advanced electricity market system in Europe Ireland Single Electricity Market
Next Project: Texas Nodal Market Operations ABB has been selected by ERCOT to replace the Areva Market Systems in the new $200m Texas Nodal (LMP) Market Project is just starting
TexasNodal Market Operations Market Design: • Congestion Revenue Rights (PTP Options, Obligations, Flowgates) • Day-Ahead Energy and Ancillary Services Co-optimized Market • Daily Reliability Unit Commitment (DRUC) • Hourly Reliability Unit Commitment (HRUC) • Security Constrained Economic Dispatch every 5 minutes • 15 minute settlement • Resource-Specific Offers, Congestion management resource-specific • Actual Shift Factors for Resources • Nodal Locational Marginal Prices (LMP) for Generation • Zonal weighted LMPs for Loads
Robb Pike Supervisor, SMD2 New York ISO 3890 Carman Road Schenectady, NY 12303 518-356-6156 ABB Market Operations References Kim Ib-Kyung General Manager IT Department Korea Power Exchange 167 Samsung-Dong Seoul Korea 82-2-3456-6590 Greg Ford VP, Market Operations California ISO 151 Blue Ravine Rd Folsom California 916-351-2344 Bill Limbrick CIO Ontario IESO Station A, Box 4474 Toronto ON M5W 4E5 Canada 905-403-6923 Ms. Dora Guzeleva Manager, Market Administration Western Australia IMO Level 22, 221, St George’s Terrace Perth, WA – 6000 61-8-9420-5617 Lasse Holopainen Vice President Market Operations Philippines WESM 9th Flr Robinsons Tower ADB Ave, Ortigas Center Pasig City Philippines 632-631-8734 Jonathan O’Sullivan Project Director ESB National Grid All Ireland Electricity Market 27 Lower Fitzwilliam Street Dublin 2, Ireland 353-676-5831 Cao Mao Sheng Project Manager State Power East China 201 Nanjing Road East Shanghai, China 021-6329-0000-2473