1 / 15

Summary: ABB Suite of Power Transmission Test Cases

Explore ABB's suite of power transmission test cases, including scenarios related to voltage collapse. This includes tap-controlled load generators, line tripping, load recovery, and generator field limit activation. The goal is to stabilize all voltages, minimize load shedding, and control voltage within specific limits.

febner
Download Presentation

Summary: ABB Suite of Power Transmission Test Cases

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Summary:ABB Suite of Power Transmission Test Cases Mats Larsson Corporate Research ABB Switzerland Ltd. Jan 19, 2004

  2. Tap Controlled Load Generator Voltage 1.05 Overload limit reached 1 0.95 Tap Changer Control 0.9 0 100 200 300 400 Collapse Scenario • Line tripping (L3) after 100 s • Inherent Load Recovery • Tap Changer Tries to Restore Voltage • Generator field limit activated at 286 s • Collapse

  3. Control Objectives • Stabilize all voltages within 0.9 - 1.1 p.u. • Use minimal amount of load shedding • Control voltage at bus 4 as close as possible to 1 p.u. • Capacitor and tap changer control can be used freely

  4. “Medium Scale” ABB Test Case • Three copies of small case • Similar control objectives • Recovery dynamics in : • load (continuous) • Transformers (discrete) Inputs: • Line impedances (disturbance) • 3 Capacitors • 3 Voltage Refs. Transformer (optional) • 3 Load shedding Outputs: • 3 Load voltages • 2 Generator field voltages

  5. Collapse in 400 secs Case 1 – Tripping of Lines Vload[2] Vload[3] 1 0.9 0 100 200 300 400 GEfd[2] GEfd[3] 1.8 1.7 1.6 0 100 200 300 400 pos[2] pos[3] 15 10 5 0 0 100 200 300 400

  6. Cap switch at 100 secs stabilizes Case 2 – Cap Switch in Area 2 Vload[2] Vload[3] 1.05 1 0.95 0.9 0 100 200 300 400 GEfd[2] GEfd[3] 1.8 1.7 1.6 0 100 200 300 400 pos[2] pos[3] 6 4 2 0 100 200 300 400 System.C2.step 1 0 0 100 200 300 400

  7. Case 3 – Tap Reference Change (-5%) Vload[2] Vload[3] 1 0.98 0.96 0.94 0 100 200 300 400 GEfd[1] GEfd[2] 1.8 1.7 1.6 0 100 200 300 400 pos[2] pos[3] 6 4 2 0 0 100 200 300 400 • Tap reference at 100 secs stabilizes

  8. Case 4 – Second line trip Vload[2] Vload[3] 1 0.8 0.6 0.4 0 100 200 300 400 GEfd[1] GEfd[2] 1.8 1.75 1.7 1.65 1.6 0 100 200 300 400 pos[2] pos[3] 12 8 4 0 100 200 300 400 • No longer stable ...

  9. Case 5 – Added load shedding at bus 3 Vload[2] Vload[3] 1 0.96 0.92 0 100 200 300 400 GEfd[1] GEfd[2] 1.8 1.7 1.6 1.5 0 100 200 300 400 pos[2] pos[3] 4 2 0 0 100 200 300 400 • Additional load shedding stabilizes

  10. Model Complexity • 6 disturbance inputs - (0,1,2) Control inputs: • 3 capacitors - (0,1) • 3 load shedding – (0,1,2,3) • 3 tap voltage refs – (0.8–1.2) Continuous dynamics: • 3 loads (2 dynamic states each) Discrete dynamics: • 3 transformers (3 states each) • 2 generator limiters (2 states each)

  11. Possible work on new model • Scaling of Model-predictive approaches (ETH, Grenoble?) • Testing of decentralized schemes (Lund, Grenoble) • Requests for customized versions welcome ...

  12. Large scale case – CIGRE Nordic 32 • 52 Discrete control inputs • Load shedding • Generator voltage setpoints • Tap changers • 10 Controlled outputs • Load voltages • 67 Constrained outputs • All voltages, generator currents • State-space ~ 1041 nodes

  13. Generator Trip – No Emergency Control 4012 • At 10 s – Gen 4062 Trips • Lost generation compensated by hydro units in the north • Increased losses in transmission corridor, lower voltage in southern region • Generators in the south increase reactive power production • At 30 s – Gen 1043 and 4042 at limit • Voltage support lost in middle and southern parts 4042 • At 50+ s – Tap changers restore load • Further voltage decrease • Collapse at 180 s 1043 4062

  14. Generator Trip – Model Predictive Control Generator trip 1 0.95 Voltage (p.u.) 0.9 0.85 V1043 V4012 V4042 0.8 0 100 200 300 400 500 Time (sec)

  15. Constraint Management 1.1 1.05 1 Armature Currents 0.95 0.9 0.85 200 400 600 800 1000

More Related