1 / 9

RECLAMATION

RECLAMATION. Managing Water in the West. Power O&M Program Great Plains Region. Mid-West Electric Consumers Association Board of Directors Meeting. Mike Ferguson, Power O&M Manager Great Plains Region. Oacoma, SD June 13, 2017. RECLAMATION. Managing Water in the West.

lynde
Download Presentation

RECLAMATION

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RECLAMATION Managing Water in the West Power O&M Program Great Plains Region Mid-West Electric Consumers Association Board of Directors Meeting Mike Ferguson, Power O&M Manager Great Plains Region Oacoma, SD June 13, 2017

  2. RECLAMATION Managing Water in the West POWER RAX PROJECTS • MT ELBERT POWERPLANT REHABILITATION • DECREASED SCOPE (No Unit Rehabs/Rewind, SS, Controls • ADDRESSING ISSUES (Relays, Cooling Water, Crane, Seals, SFC) • CONTINUING WITH DESIGNS / SPECS • DECREASED COST ($68 to $20 Million / Balance Shifted to CF) • SCHEDULE ACCELERATED (FY 2021)

  3. RECLAMATION Managing Water in the West • YELLOWTAIL REWIND / REHAB • UNIT 3 COMPLETED & IN SERVICE • UNIT 1 REWIND COMPLETED BUT BALANCING ISSUE • Disassembly & Shrink Rim • September 2017 Target Date to Re-Start Commissioning • CANYON FERRY PLANT REHAB • UNIT 1 WINDING FAILURE – Repaired and De-Rated Unit • PLANT ASSESSMENT WITH TVA ASSISTANCE • ASSESSMENT REPORT IN JULY – Decisions on Recommendations • FINALIZE SCOPE, COST ESTIMATE, SCHEDULE

  4. RECLAMATION Managing Water in the West • CANYON FERRY SWITCHYARD RELOCATION • SAFETY ISSUES • ENVIRONMENTAL ISSUES • EQUIPMENT ISSUES – OCB’s 64 Years Old • PARTNERING WITH WAPA TO DEFINE SCOPE, COST, SCHEDULE • BOYSEN & SEMINOE PLANT REHABS • PLANT ASSESSMENTS WITH TVA ASSISTANCE • ASSESSMENT REPORTS IN JULY 2018 • FINALIZE SCOPE, COST ESTIMATE, SCHEDULE

  5. RECLAMATION Managing Water in the West • OVERALL POWER WORKPLAN • 45 POWER RAX PROJECTS BEING WORKED ON IN FY2017 • CBT Plants Unit Vibration System Addition • Green Mountain Penstock Relining • Pole Hill Penstock Expansion Joint Packing Replacement • Flatiron Unit Air Cooler Replacement • Flatiron Penstock Interior Coating Repairs • Flatiron High-Voltage Cable Tunnel Asbestos Abatment • Flatiron Protective Relay Replacement • Canyon Ferry Powerplant Roof Replacement • Canyon Ferry Control Room Asbestos Ceiling Replacement • Canyon Ferry Low Voltage Distribution System Replacement

  6. RECLAMATION Managing Water in the West • OVERALL POWER WORKPLAN • 45 POWER RAX PROJECTS BEING WORKED ON IN FY2017 • Yellowtail Low Voltage Distribution System Replacement • Yellowtail Powerplant Sump Pumps Replacement • Yellowtail Afterbay Sluiceway Stoplogs Refurbishment • Fremont Canyon Unit Spiral Case Recoating • Guernsey Spillway Gate Refurbishment • Guernsey Powerplant Penstock Surge Tank Recoating • Seminoe Facility Road Repair (Partnering with State/Federal) • Shoshone Powerplant Roof Replacement

  7. RECLAMATION Managing Water in the West • OVERALL POWER WORKPLAN • 11 PROJECTS IDENTIFIED TO BE COMPLETED IN FY 2017 • Carter Lake Fiber Optic System Addition • Flatiron Gatehouse/Gauging Station Fiber Optic System Addition • Marys Lake Runner Replacment Design/Spec • Big T Dille Diversion Structure Repair • Canyon Ferry Elevator Replacement • Yellowtail Dam Formed Drain Cleaning • Glendo Dam Spillway Safety of Dams Modification • Glendo Powerplant Bridge Crane Radio Control Addition • Heart Mountain Powerplant Bridge Crane Replacement • Kortes Powerplant AC/DC Distribution System Replacement • Seminoe Dam Stilling Basin & Tailrace Concrete Repairs

  8. RECLAMATION Managing Water in the West • WSPC CUSTOMER UPFRONT FUNDING • FY 2015 = $22.5 MILLION • FY 2016 = $29.6 MILLION • FY 2017 = $33.3 MILLION • FY 2018 = $12 - $15 MILLION • THANK YOU !! • P-S PROJECT USE PUMPING POWER • 25 CONTRACTS DUE FOR RENEWAL IN 2020 • EXISTING 2.5 MILLS/KWH WILL GO UP TO CURRENT RATE • CURRENT RATE AT 16.17 MILLS/KWH

  9. RECLAMATION Managing Water in the West • POTENTIAL COST ALLOCATION CHANGES • WYAO MICROWAVE SYSTEM • WYAO SCADA SYSTEM • INITIATE A CURRENT USE COST ALLOCATION STUDY • POTENTIAL CHANGE FROM 100% POWER TO MULTIPURPOSE • FINAL DECISION BY REGIONAL DIRECTOR

More Related