An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ABC130 and HCC Submissions F.Anghinolfi ABC Final Design Review

  2. ABC130 (& HCC) Submission on MPW • On MPWs • Regular MOSIS MPW on 4th May 2013 (reachable for ABC130, for HCC ?) • Next regular MOSIS MPW on 4th August 2013 (reachable for HCC) • Additional quantities on request (but costs) ABC Final Design Review

  3. ABC130 Submission on … • Shared Engineering Run (ABC + TDCpix) • ABC : Shared Engineering run with the NA62/TDCpix submission (forecast 1Q 2013) • Additional Eng. Run wafers at 3.6KUSD each (120chips/w) • Needs Synchro btw TDCpix(NA62) and ABC (for submission in Feb-March. 2013, FDR January-Feb 2013 for both ASICs) ABC Final Design Review

  4. ABC130 & HCC Submission Scenario 2 • Shared Engineering Run (ABC + TDCpix) Additional Eng. Run wafers at 3.5KUSD each (120chips/w) Production Run wafers at 2.5KUSD each (120chips/w) ABC Final Design Review

  5. ABC130 & HCC Submission Scenario 2 • Shared Engineering Run (ABC + TDCpix) Eng. Run + 1 Production run = 3720 chips Eng. Run + 2Production run = 6120 chips Eng. Run + 3 Production run = 8520 chips ABC Final Design Review

  6. Separate HCC Production • Option for HCC if ABC is submitted separately MPW Mosis : 40 chips @ 37KUSD “Small Quantity Production” with MOSIS (one 24 wafers lot of HCC-mainly reticle) at 100K-150KUSD range (should provide much more ASICS than the 900 requested ….) Addition of (worst case cost) 7000 ABC (on shared Eng. Run with TDCPix) delivery plus HCC small Production Run = (322 + 150) KUSD ~ 472KUSD ABC Final Design Review

  7. ABC130 &HCC Engineering Run • Engineering Run (ABC + HCC) • Additional Eng. Run wafers at 3.5KUSD each • Production Run wafers at 2.5KUSD each • HCC drives the schedule ABC Final Design Review

  8. ABC130 &HCC Submission Scenario 3 • Engineering Run (ABC + HCC) • One engineering run comes short (but close ..) to 7000 Cost 475KUSD ABC Final Design Review

  9. ABC130 Submission Scenario • ABC independent of HCC • Regular MOSIS MPW on 4th May 2013 (reachable for ABC130, probably not for HCC) • Shared Engineering run with the NA62/TDCpixsubmission (forecast 1Q 2013) • With HCC : • Engineering Run, attached to HCC schedule • Independent HCC : • Small quantity production possible through MOSIS ABC Final Design Review