MRSO Update Aileen O’Connor MRSO
Generation Loss Adjustment Factors (LAFs) • MRSO committed to update the IGG on an issue concerning generation loss factors • Since go-live Eirgrid has been providing data for the 7 price affecting generators in the market • This data is needed on a 7 day basis by SEMO because it is an input to the price • Up to now their systems have not been able to apply DLAFs to data from these 7 sites • This situation is now corrected from 1st Jan (Mod 43_08) • This has no significant impact on the retail market
NQH to QH • MRSO recently moved approx 40 sites to QH with a start date of 1st Jan 09 • There are approx 100 sites that PDS/MRSO hope to move before the next audit is completed, which is due the end of June 09.