1 / 4

Russell Cave Elementary – Renovation

Russell Cave Elementary – Renovation. Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date: August, 2010 Contract Sum: $5,001,150 Change Orders to Date (1): $0 Current Phase: 1 (On Schedule) Estimated Completion: 16%.

mari
Download Presentation

Russell Cave Elementary – Renovation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date: August, 2010 Contract Sum: $5,001,150 Change Orders to Date (1): $0 Current Phase: 1 (On Schedule) Estimated Completion: 16% July 2009

  2. Russell Cave Elementary – Renovation Rendering of Final Façade July 2009

  3. Russell Cave Elementary – Renovation Work Completed in Last 30 Days: Exterior concrete block walls are being installed. Interior of Kitchen/Cafeteria has been demolished and renovation has begun. Renovation of (4) classrooms on the south side has begun. Concrete slab at the new addition has been poured. Masonry restoration on the exterior of the original building in process. Existing elevator has been upgraded. Current Work Effort (July): Roof trusses at the new additional will be set. Kitchen/Cafeteria renovation will be completed. Interior work on the new addition and the (4) classrooms on the south side will continue. They are scheduled to be completed in October. Complete new electrical and mechanical systems in Kitchen/Cafeteria. July 2009

  4. Russell Cave Elementary – Renovation New Addition New Addition Interior of Cafeteria Masonry Restoration July 2009

More Related