Improved Exhibit 300s Through Better Project Management By Kimberly Smith, PMP
Agenda • Mapping the PMBOK and CPIC processes • Review the significant impacts per phase • Discuss impacts to the E300 • Wrap-up
Initiate Plan Monitor & Control Execute Close Mapping the PMBOK and CPIC processes Pre-Select/ Select Control Evaluate
Initiation ~ Pre-Select /Select • Evaluate the idea • Determine if an agency need is being met • Be sure there is a benefit to the Government • Justified Cost; Identified Risk; Evaluated Alternatives; Scope Defined • Approval of the investment
Ensure consistency with A-94* Create a template for reusability Evaluate viable options Seek options beneficial to the government E300 Impacts: Basis for the summary of spending Initiate The Cost Benefit Analysis • Ensure the purpose of the investment • Substantiate the business case • Gain approval • Establish Scope • Know the Risk
Ensure the purpose of the investment • Substantiate the business case • Gain approval • Establish Scope • Know the Risk Initiate Scope Management • Create description • Determine deliverables • Establish boundaries • Determine development lifecycle • Gain Stakeholder validation • Document and track E300 Impacts: Established lifecycle milestones
Ensure the purpose of the investment • Substantiate the business case • Gain approval • Establish Scope • Know the Risk Initiate Risk Management • Evaluate risk • in Scope • in Cost • in Milestones • in Schedule E300 Impacts: Enable risk adjusted cost & schedule; support documents
Planning ~ Pre-Select /Select • Create Project Management Plan • Validate/create the lifecycle costs • The acquisition strategy is developed • The performance baseline is set • The performance measures are identified
Develop Project Management Plan • Validated lifecycle costs • Acquisition/Development details • Performance measure • Develop Project Management Plan • Validated lifecycle costs • Acquisition/Development details • Performance measure Plan Plan • Develop Project Management Plan • Validated lifecycle costs • Acquisition/Development details • Performance measure Plan The Plan • Develop integrated Project Management Plan Including, but not limited to: • WBS • Schedule • Integrated support plans • Performance baseline • Risk documentation E300 Impacts: Basis for the milestone plan
Develop Project Management Plan • Validated lifecycle costs • Acquisition/Development details • Performance measure Plan The Performance Baseline • Create an integrated milestone plan based on the WBS • Verify all the lifecycle is represented in the baseline • Establish the earned value management methodology E300 Impacts: Establishes the support for the baseline
Execute/Monitor & Control ~ Control • Carry out the activities in the plan • Assess the progress of the project • Track performance measure • Evaluate risk • Update and track EVM
EVM • Track progress against the plan • Make necessary adjustments • Update EVM routinely • Understand the receiving audience E300 Impacts: Measured from the milestone plan • Execute the plan • Monitor project progress • Track performance measure • Update and evaluate risk • Update and track EVM • Performance measure Execute /Control
Risk Management • Execute the risk management plan • Review for effectiveness • Update the risk list • Review for impact to the cost and schedule E300 Impacts: Establish risk responses and support document • Execute the plan • Monitor project progress • Track performance measure • Update and evaluate risk • Update and track EVM • Performance measure Execute /Control
Evaluate/Close • Validate the goals • Close out acquisition • Review lessons learned • Document the return on the investment • Finalize the project repository with final updates • Evaluate the performance gap • Perform operational analysis • Retire the system
Review Lesson Learned • Determine if processes should be updated • Compare the progress against the baseline • Share the knowledge such that oversight bodies gain insight • Validate the goals • Review lessons • Finalize project documents • Close out acquisitions • Operational Analysis Evaluate & Close
Operational Analysis • Review investment effectiveness • Identify improvement opportunities • Finalize when the project is complete E300 Impacts: Look for opportunities to change states • Validate the goals • Review lessons • Finalize project documents • Close out acquisitions • Operational Analysis Evaluate & Close
Wrap-Up • PMBOK based Project Management provides the basis for the E300 baseline • The chosen alternative • The milestones • The lifecycle cost • E300 discipline • Promotes good stewardship • Keeps the Project Manager proactive