110 likes | 217 Views
TPC Commissioning ALICE Technical Forum, CERN, 8 th March 2007 L. Musa. Outline Pre-commissioning above ground (2006) Preparing for the commissioning in the cavern (2007). TPC pre-commissioning above ground (2006).
E N D
TPC Commissioning ALICE Technical Forum, CERN, 8th March 2007 L. Musa • Outline • Pre-commissioning above ground (2006) • Preparing for the commissioning in the cavern (2007)
TPC pre-commissioning above ground (2006) • A first phase of TPC Commissioning was carried out above ground in the course of 2006 • Jan-Mar installation of SSW and FEE • April start of gas system • May HV (100KV) applied to FC • Jun–Dec test of all sectors (in pairs) • Each sector was operated continuously over a period of 40 hours and verified with • calibration pulser, • cosmic-muon trigger detector ACORDE • UV laser system for the generation of tracks in the detector Many TPC and ALICE sub-systems (e.g. cooling, gating grid pulser, temperature sensors, DCS, Trigger, DAQ, HLT and Offline) have been part of this commissioning programme ~300 man shift, 3588 runs, ~24 TB in CASTOR
TPC pre-commissioning above ground (2006) ALICE COSMIC Trigger (ACORDE) Laser tests Cosmic tests Only two sectors can be instrumented at a time with • Low Voltage Power Supplies • Cooling Commissioning objectives • Test functionality of all components • gas stability, noise, signal tails, gain homogeneity, space resolution, etc. Each pair of sectors continuously operated over 40 hours
TPC pre-commissioning (2006); some results – Noise measurements (PASAnoise2 + ADCnoise2) = 0.70 ADC counts r.m.s. of the pedestals (sNOISE) is below 1 ADC count as required in the Technical Design Report
TPC pre-commissioning (2006); some results – Cosmic tracks A B space point resolution as function of z position (cut on inclination angle tan(f) <0.05) A TDR value: 210mm / cm • Q total (total charge in the cluster) as function of z position • relative decrease over the full TPC length: ~7% • decrease due to electron capture and threshold effect B TDR value 1% / m per ppm of O2 3 ppm of O2 measured with gas chromatograph
TPC pre-commissioning (2006); some results – Laser tracks Design Measured Drift velocity = 2.73 cm/mm agreement with drift monitor detector (Goofie)
Moving the TPC into the ALICE magnet Jan ‘07 TPC has been lowered in UX25 • After the alignment with respect to the beam line, the TPC has been put in parking position. • Feruary, alignment of SSW with respect to endplate, and test of the connection of FEE to the endplate (calibration pulser) All 4356 FECs and 216 RCUs are working All 26136 kapton cables are properly connected to the pad plane
Alignment of SSW wrt endplate within mm Displacements of SSW wrt endplate should not exceed 3mm ~7 mm Readout Chamber X Front End Card kapton cable Y Z
Preparing for Commissioning in UX25 • In 2006 all efforts mostly devoted to pre-commissioning in SXL2 • Still some hardware components to be finalized and/or constructed. Two examples: • Trigger Busy Box (being finalized and tested) • Trigger&DCS Interface Unit for Laser, GG Pulser and Calibration Pulser • (starting design) • Many software components to be finalized and commissioned Some examples: • Software for the configuration and monitoring of the FEE • Interface to the FERO database • Interface to ECS • DCS for some of the sub-systems and TPC FSM (Supervisory Layer) • Data Quality Monitoring
Preparing for Commissioning in UX25 • Cables and cooling pipes (before connecting to the TPC all cables and cooling lines will be tested) • cables from crates to backframe (C side): April • test of cables @ backframe (C side): May • TPC wil be moved to final position (interaction point) and connected to the gas system in June (~about 1 month before reaching nominal conditions) • Connection of TPC C side June • Connection of TPC A side Aug
TPC commissioning - Milestones • Test of FEE & ROC (C-side) • Turn on FEE July • Test of FEE, Trigger, DAQ, DCS and all services July • Test of ROCs July - Aug • Test of FEE & ROC (A-side) • Turn on FEE Sep • Test of FEE, Trigger, DAQ, DCS and all service Sep • TPC Commissioning with cosmic tracks, laser Sep - Oct and Kr (under study) • ALICE Commissioning Oct -Nov