80 likes | 191 Views
Fort Stanwix National Monument Energy Audit. Detailed Design Review Friday, February 20 th , 2009 Customer: FSNM, contact: Debbie Conway Guide: Brian Thorn P09453. Project Description. Customer Needs. Rational for Customer Needs based on: Project readiness packet
E N D
Fort Stanwix National Monument Energy Audit Detailed Design Review Friday, February 20th, 2009 Customer: FSNM, contact: Debbie Conway Guide: Brian Thorn P09453
Customer Needs • Rational for Customer Needs based on: • Project readiness packet • December 2nd phone interview with FSNM – Debbie Conway • December 13th onsite visit with Debbie and Todd • Key statement: reduce current total cost of energy at FSNM to offset the impact of potential ‘green’ energy opportunities and conservation measures
Budget Update • Modeling Software - $0 • Free download from DOE • Travel – 2 onsite visits • 1st visit: 1 car R/T, no meals • 2nd visit: 2 cars R/T, meals • MSD2 Direct Costs • Renewable demo supplies
Moving Forward - Spring Quarter • Order Solar System Wk 11 [Winter Quarter] • Determine energy savings per ECM with detailed breakdown • Economic Analysis • Energy Assessment Report • Install Solar System • Installation, maintenance, test plan
Risks • Robustness of renewable demo • Lead time on Solar demo parts • Balancing education and entertainment aspects • Detailed ECM impacts • eQuest model assumptions • Funding • Proximity to FSNM