1 / 16

RPEWG Report to PCC

RPEWG Report to PCC. Seattle, WA June 2003. Agenda SRP Double PV-WW PBRC Adjustment Seven Step Process Phase 1 PBRC Adjustment Review: Robust Line Design. SRP Double PV-WW PBRC Adjustment. Request.

mercer
Download Presentation

RPEWG Report to PCC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RPEWG Report to PCC Seattle, WA June 2003

  2. Agenda • SRP Double PV-WW PBRC Adjustment • Seven Step Process • Phase 1 PBRC Adjustment Review: • Robust Line Design June 2003

  3. SRP Double PV-WW PBRC Adjustment Request • Salt River Project requests a PBRC Adjustment from Category C to Category D for the double Palo Verde to Westwing line outage • Evaluated using Seven Step Process June 2003

  4. WW SRP Double PV-WW PBRC Adjustment Step 1: Provide Project Description Detailed report provided. June 2003

  5. SRP Double PV-WW PBRC Adjustment Step 2: Identify the Statistical Base • PV-WW performance has been excellent • No double outage • One line 2 outages and second line 0 outage • Sample developed from SGS data for SW EHV lines • Very few SW EHV line on shared corridors June 2003

  6. SRP Double PV-WW PBRC Adjustment Step 3: Uncorrected MTBF • Sample from matching terrain, weather conditions and structure type • 39 circuits • MTBF N-2 Weibull method of analysis • Coincident Independent events = 500 years • N-2 Dependent event analysis = NA June 2003

  7. SRP Double PV-WW PBRC Adjustment Step 4: Corrected Estimate of MTBF 1. MTBF analysis ……….. 2. Robust Line Design Features • #1. MTBF Analysis: • Lines w/<1.5 outage/year except Mead-Phoenix included • 17 corridors • 2 instances of N-2 events • N-2 Weibull MTBF • Coincident Independent events = 2,824 years • N-2 Dependent event analysis = NA June 2003

  8. SRP Double PV-WW PBRC Adjustment Step 4: continued • #2. Robust Line Design Features: • RPEWG used its Robust Line Design Features working paper to evaluate the robustness of the line design. • The analysis compared thirteen factors in examining the line robust features. • Two areas of concern were critically evaluated • Mead Phoenix line crossing over PV-WW • Circuit separation preventing towers falling into each other June 2003

  9. SRP Double PV-WW PBRC Adjustment Step 4: continued The conclusion from the Robust Line Design Features evaluation was that the PV-WW lines meet or exceed the Robust Line Design Features required for PBRC adjustment. June 2003

  10. SRP Double PV-WW PBRC Adjustment Step 5: Exposure Analysis • 2% of time double PV-WW will be critical outage  • Existing safety net will remain in place during time when PV-WW double outage is the critical outage June 2003

  11. SRP Double PV-WW PBRC Adjustment Step 6: Consequences of Outage • System safety net will remain in place  • Operating studies show that voltage dip with PV-WW outage will not exceed 30% voltage dip criterion June 2003

  12. SRP Double PV-WW PBRC Adjustment Step 7: Recommendation • RPEWG members voted to approve and recommend that PCC also approve SRP’s request for PBRC Adjustment for the double PV-WW line outage from Category C to Category D.   • RPEWG cannot make a recommendation regarding MTBF of greater than 300 years. June 2003

  13. SRP Double PV-WW PBRC Adjustment PCC discussion & vote June 2003

  14. Phase 1 PBRC Adjustment Review: • Robust Line Design  June 2003

  15. Risk Factors The following is a list of risk factors to be considered in ROW planning for cases where it is the goal that the N-2 outage be of very low probability. Generally risk increases with common ROW distance. R1 Risk of fire affecting both lines R2 Risk of one tower falling into another line R3 Risk of a conductor from one line being dragged into another line R4 Risk of lightning strikes tripping both lines R5 Risk of an aircraft flying into both lines R6 Risk of station related problems resulting in loss of two lines for a single event R7 Risk of snow or earth slides R8 Risk of loss of two lines due to an overhead crossing June 2003

  16. Design Variables The following are design variables which affect the credibility of each of the above Risk Factors: V1 Substation breaker configuration (R6) V2 Circuit centerline spacing (R1,R2,R3,R8) V3 Span length (R3) V4 Tower design (R2,R7,R8) V5 Use of shield wires for lightning (R4) V6 Conductor support systems (R8) V7 Use of dead-end versus suspension towers (R3) V8 Use of single pole reclosing (R4) V9 Vegetation management (R1) V10 Fire watch curtailments (R1) V11 Shortening of line on common ROW (R1-R8) V12 Tower grounding (R4) V13 Protective relaying design and settings (R6) June 2003

More Related