1 / 8

TG1 Closing Report for March 2013

TG1 Closing Report for March 2013. Authors:. Date: 2013-03-21.

minty
Download Presentation

TG1 Closing Report for March 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TG1 Closing Report for March 2013 Authors: Date:2013-03-21 Notice:This document has been prepared to assist IEEE 802.19. It is offered as a basis for discussion and is not binding on the contributing individual(s) or organization(s). The material in this document is subject to change in form and content after further study. The contributor(s) reserve(s) the right to add, amend or withdraw material contained herein. Mika Kasslin, Nokia

  2. Abstract This is TG1 closing report from March 2013 plenary meeting in Orlando, FL, USA Mika Kasslin, Nokia

  3. Agenda and Results • The TG focused on comment resolutions with 59 technical and 9 general comments open • The TG heard several contributions related to the comments and many of them were accepted as comment resolutions • All the comments were addressed • This gives the TG an opportunity to ask the WG chair to submit an updated draft into WG re-circulation LB • Draft meeting minutes available in 19-13/0037r3 • Approved comment resolutions available in 19-12/0204r9 Mika Kasslin, Nokia

  4. What’s Next? • The TG requested the TG editor to prepare by April 4th, 2013, a new 802.19.1 draft for WG re-circulation LB • The TG kindly asks the 802.19 WG chair to start a 25-day WG Re-circulation Letter Ballot on a new 802.19.1 draft no later than April 8th, 2013 Mika Kasslin, Nokia

  5. Tentative Schedule • wk-Mar25 • wk-Apr01: New draft released by the TG editor • wk-Apr08: WG re-circulation ballot opens • wk-Apr15 • wk-Apr22 • wk-Apr29: WG re-circulation ballot closes • wk-May06 • wk-May13: May 2013 interim meeting Mika Kasslin, Nokia

  6. Teleconferences • The TG will have no teleconferences before the May 2013 interim Mika Kasslin, Nokia

  7. May 2013 Interim Objectives • Continue comment resolutions and resolve all the remaining comments • After this meeting we have still 63 technical and general comments open • Have the draft prepared for a recirculation WG LB after the March 2013 meeting so that the ballot closes before the May 2013 interim • Decide on whether the 802.19.1 draft is ready to be made available for IETF PAWS Mika Kasslin, Nokia

  8. Targeted TG1 Timeline • Second Working Group Letter Ballot: October 2012 • Recirculation Letter Ballot: March 2013 • Recirculation Letter Ballot: July 2013 • Form Sponsor Ballot Pool: July 2013 • Initial Sponsor Ballot: November 2013 • Recirculation Sponsor Ballot: March 2014 • Final WG/EC Approval: July 2014 • RevCom/Standards Board Approval: September 2014 Mika Kasslin, Nokia