1 / 12

Proposed Layouts for Signal, LV and HV cables in YB+1

Proposed Layouts for Signal, LV and HV cables in YB+1. Piyush Verma TIFR, India. All the Services of Muons as well as HO on +Z side. Three options shown. In all the options Signal Cables from Sector 6 and Sector 4 go through the megatile covers and exit on sector 2.

monty
Download Presentation

Proposed Layouts for Signal, LV and HV cables in YB+1

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Proposed Layouts for Signal, LV and HV cables in YB+1 Piyush Verma TIFR, India

  2. All the Services of Muons as well as HO on +Z side. • Three options shown. • In all the options • Signal Cables from Sector 6 and Sector 4 go through the megatile covers and exit on sector 2. • Signal Cables from Sector 8 and Sector 10 go through the megatile covers and exit on sector 12.

  3. Full View of YB+1 from +Z side.

  4. Option1

  5. Option1 • Signal Cables go under MAB between sector 1 and sector 12 for lower half and under MAB between sector 2 and sector 3 for upper half. • Cross section required for signal cables under each MAB = 27mm x 27mm. • HV cables go along the Copper tubes along radial support for each sector having RBX. • HV cable cross section = 12 dia. • 2 LV cables and Slow control cable routed on the face of sector having RBX. • 2 LV + 1 Slow control c/s = 20 dia. + 2 mm tolerance => 22 mm. • No extra length looped and kept on frame considered. LV +slow control to have disconnect box.

  6. Option1 (remarks) • Signal Cables : • Space under MAB only 21 mm under present scenario. • Also signal cables have to pass over Yoke cooling pipe under the MAB. • May be possible if we spread out the signal cables. • HV Cables: • As these run along copper tubes, there are some tight points. • HV cables require minimum of 150 mm bending radius. Routing along copper tubes is having a lot of Zig-Zag. Achieving the min. bend radius may be difficult. • Is routing of HV line along with Copper tubing advisable? • LV Cables : • Extra cost for disconnect box.

  7. Option2

  8. Option2 • Signal Cables go on the face of sector 12 for lower half and on sector 2 for upper half (same as YB+2). Extra length of ~2 M looped and kept on structure outside Yoke iron. • Cross section required for signal cables = 27mm x 27mm. • 2 LV cables and Slow control cable routed on the face of sector having RBX. • 2 LV + 1 Slow control c/s = 20 dia. + 2 mm tolerance => 22 mm. • 2M extra length looped and kept on Structure along with Signal Cables. No disconnect box. • Total c/s on face of Sectors 2 and 12 = 49 mm wide x 27 mm high. • HV cables go along the Copper tubes along radial support for each sector having RBX. • HV cable cross section = 12 dia.

  9. Option2 (remarks) • Signal Cables and LV+Slow Control Cables : • No effect of MAB location for routing from sector to patch panel. • Fixing of signal cables less complicated as the go on existing cable trays fixed for muon services. (No extra drilling of holes on Yoke Iron). • No extra cost for disconnect box. • Due to extra length HO System and Muon System will be disconnected for maintenance.

  10. Option3

  11. Option3 • Signal Cables go on the face of sector 12 for lower half and on sector 2 for upper half (same as YB+2). Extra length of ~2 M looped and kept on structure outside Yoke iron. • Cross section required for signal cables = 27mm x 27mm. • 2 LV cables and Slow control cable routed on the face of sector having RBX. • 2 LV + 1 Slow control c/s = 20 dia. + 2 mm tolerance => 22 mm. • HV cables also routed on the face of sector having RBX along with LV Cables and Signal Cables. • HV cable cross section = 12 dia. • 2M extra length looped and kept on Structure along with Signal Cables. No disconnect box. • Total c/s on face of Sectors 2 and 12 = 61 mm wide x 27 mm high. • Total c/s on face of Sectors 4, 6, 8 and 10 = 35 mm wide x 22 mm high.

  12. Option3 (remarks) • Signal Cables, HV and LV+Slow control Cables : • No effect of MAB location for routing from sector to patch panel. • Fixing of signal cables less complicated as the go on existing cable trays fixed for muon services. (No extra drilling of holes on Yoke Iron). • No extra cost for disconnect box. • Fixing of HV cables also becomes very simple. • Due to extra length HO System and Muon System will be disconnected for maintenance.

More Related