Sarasota Memorial Health Care System Projects Update Neighborhood Advisory Council June 24, 2010. Agenda:. CEP Status Construction Phasing Construction Status Surgery Vertical Expansion Bed Tower Package Medical Arts Building Construction Web Cam. CEP Status:.
E N D
Sarasota Memorial HealthCare SystemProjects UpdateNeighborhood Advisory CouncilJune 24, 2010
Agenda: • CEP Status • Construction Phasing • Construction Status • Surgery Vertical Expansion • Bed Tower Package • Medical Arts Building • Construction Web Cam
CEP Status: • Building Construction is complete • Sound testing is complete and in compliance. • Fully operational CEP: Done!
Project Phasing – 2 New CEP Completed Information Systems Complete – 5-Service Central Receiving Complete – 1-Waldemere Wound Care – 2-Waldemere On-Call – 4-Central Observation Complete – 9-East Surgery/CS Vertical Expansion Interim Moves for Surgery Support & Pathology Temporary ECC Turn-around & Canopy Temporary Entry/Exit at Waldemere Garage Demolish Old CEP Temporary Main Entrance Canopy
Project Phasing – 3 Wound Care – 2-Waldemere Temp Main Entry Turn-around & Canopy On-Call – 3-East Surgery/CS Vertical Expansion Interim Moves for Surgery Support & Pathology Temporary ECC Turn-around & Canopy
Project Phasing – 4 Wound Care – 2-Waldemere Temp Main Entry Turn-around & Canopy On-Call – 3-East Surgery/CS Vertical Expansion Moves for Surgery Support & Pathology Complete Demolish Portion of Critical Care Tower Temporary ECC Turn-around & Canopy Complete Sitework & Temporary Drive
Project Phasing – 5 Temp Main Entry Turn-around & Canopy Demolish Northeast Tower Main Entry Canopy Structure for Bridge, Elevator & Stair On-Call – 3-East Surgery/CS Vertical Expansion ECC Vestibule, Canopy and Drop-off Complete Sitework & Temporary Drive
Surgery Vertical Expansion Status: • The Crane is set up on Arlington St. • Structural Steel Erection is in progress. • Construction of Bridge across Arlington St. will begin in August
Bed Tower Status: • Old CEP is Demolished • Temporary ECC Entry Drive Complete • Temporary ECC Entry Canopy Open • Hawthorne Street at US 41 is Closed • Underground Utilities in Progress
Bed Tower Status: • Temporary Garage Entry/Exit at Waldemere Street • Temporary Main Entry Canopy in Progress
HVI WebCam Link – http://www.smh.com/ • East Tower “green camera” Coming Soon