1 / 10

Radiation Protection aspects of the Switch-Yard operation

Radiation Protection aspects of the Switch-Yard operation. V. Donate, G. Dumont, Joachim Vollaire on behalf of DGS-RP. Outline. RP measurements Operational aspects Additional monitoring Conclusions. RP measurements.

nika
Download Presentation

Radiation Protection aspects of the Switch-Yard operation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Radiation Protection aspects of the Switch-Yard operation V. Donate, G. Dumont, Joachim Vollaire on behalf of DGS-RP

  2. Outline • RP measurements • Operational aspects • Additional monitoring • Conclusions PS-CSAP 10/10/2013

  3. RP measurements • Objective: Assess the maximum dose rate in the accessible part of the PS in case of beam loss in the BTM line and BHZ10 failure PS-CSAP 10/10/2013

  4. Measurements • PATP501(RAMSES monitor) installed in the area • Losses created by BE-OP (EN-STI had moved the stopper in the beam path) 2nd losses 2 intensities 1st losses Residual dose rate in the area Monitor out of the PS Scan PS-CSAP 10/10/2013

  5. First beam loss created • 3 pulses to the stopper (1.14e13 ppp) • Rescaling: 3.3e13 ppp and 3000 pulses/h • Pos. 1: 340 mSv/h / 0.11 mSv per pulse • Pos. 2: 155mSv/h / 0.05 mSv per pulse • Pos.3 : 700 mSv/h / 0.23 mSvper pulse Pos. 2 Pos. 1 Stopper Pos. 3 (Pos. 3 not accessible with beam) PS-CSAP 10/10/2013

  6. Scanning for worst configuration • Selected configuration : • BHZ10 off + BTM.QNO.5 off (BTP in) • Rescaling: 3.3e13 ppp and 3000 pulses/h • Pos. 1: 1.97 mSv/h / 0.7 mSv per pulse • Pos. 2: 710 mSv/h / 0.23 mSv per pulse • Pos.3 : 4.2 mSv/h / 1.4 mSv per pulse Pos. 2 Pos. 1 (Pos. 3 not accessible with beam) Pos. 3 Even for this worst case, for losses limited to a few pulses (interlock) the dose is relatively low (to be put in perspective with residual dose rate levels) PS-CSAP 10/10/2013

  7. Operational considerations • Alarm thresholds to be set according to residual dose rate when access is granted in the PS (RPO / piquet) • Short access, the dose rate decrease quickly • Status of “Porte secteur inter-zone” during technical stops and shutdown (left open ?) • Loss of flexibility in access to different areas (higher exposure…) Survey (mSv/h @ 40 cm) 26/06/2012 18/09/2012 06/11/2012 PS-CSAP 10/10/2013

  8. Missing RP monitor • Risks associated to a loss of the Linac2(4) beam (LTB) • Possible exposure of personnel in the center of the ring or SS12 area • Measurements done with full beam loss in the LTB line leads to 800 mSv/h at the center of the ring • One single monitor would protect both areas (alarm panel at both locations) Monitor PS-CSAP 10/10/2013

  9. Missing RP monitor • PATP501 paid on R2L budget anticipating the creation of this new operational mode • RP monitoring not ready to allow Switchyard operation with PS access. • Currently missing 45 kCHF to ensure proper monitoring of accessible areas in Switchyard mode (two areas currently uncovered in case of beam losses in the LTB line) ! PS-CSAP 10/10/2013

  10. Conclusions • Beam losses in the BTM line leads to limited exposure of personnel in the PS ring area (interlock SIL2) • Operational procedure to be developed (to define the alarm thresholds for the PATP501 monitor) • Problem of induced radioactivity…. which will decrease with time (need to adapt the alarm threshold)…. • Status of doors to be agreed upon (EN / BE / RP….) for different periods (shutdown, TS…) • RP is missing 45 kCHF to install the necessary monitoring for the switchyard operation mode…. • As part of the PS ventilation commissioning study air flow between the PSB and PS (smoke test ?) to see if activated air could come from the PSB PS-CSAP 10/10/2013

More Related