Sector 20 Scope of Conventional Facilities Project. Demolition of Existing 1700 ft 2 Alcove Bldg. Construction of New 2250 ft 2 Bldg. in ~ same location with 10’ extensions on ends. Steel Frame Building Modifications to existing foundation New HVAC and Electrical Service Interior Finishes
E N D
Sector 20 Scope of Conventional Facilities Project • Demolition of Existing 1700 ft2 Alcove Bldg. • Construction of New 2250 ft2 Bldg. in ~ same location with 10’ extensions on ends. • Steel Frame Building • Modifications to existing foundation • New HVAC and Electrical Service • Interior Finishes • Construction of New 300 ft2 “RF Hut” in Klystron Gallery • Some Cable Trays and Supports. Cabling to be designed by SLAC and installed by subcontractors as separate project. • Surface mounted electrical distribution in injector alcove area.
Sector 20 Installation (future) Klystron Gallery Elev 0’0” N Existing Stairs Linac tunnel Elev. -35’0”
Sector 20 Conv. Facility Construction Areas Laser Facility N RF Hut
Sector 20 Schedule & Cost • Completion of Title II drawings • January 2005 • Bid and contract with general contractor • February – March 2005 • Construction • April 2005 – April 2006) • Total Estimated Cost - $1.6M • $1.0M const, $0.2M LCW, $0.3M elec. LLP, $0.1M prep
Magnetic Measurement Facility Uses • Undulator magnet tuning – 2 magnet measuring machine test stands • Aligned with same orientation to Earth’s magnetic field as LCLS Undulator Hall. • Undulator fiducialization – large coordinate measuring machine • Cradle assembly area • Magnet storage/temperature acclimation • Work desks in lab and office space for 2 employees
MMF Building Criteria • ~4800 sq. ft. floor space (inc. ~3000 laboratory space) + mezzanine • Locate within an existing building to aid in temperature control • Adequate ceiling height for overhead cranes • Accessible for magnet delivery using trucks and forklifts • Availability of required utilities, esp. electrical service – 600A, 480v 3f
Rear Elevation Mechanical Access Roll up door for magnet delivery Staff access
MMF Schedule & Cost • Completion of Title II drawings • January 2005 • Bid and contract with general contractor • February – April 2005 • Construction • May – November 2005 (Early Finish) • February 2006 (Beneficial Occupancy) • Total Estimated Cost - $ 2.0M • $1.4M const., $0.5M elec. LLP, $0.1 M prep